Skip to content
NY State contractorConstruction & Renovation

Air-Mechanical Corporation

State contracts since 2010Updated Nov 13, 2026

Air-Mechanical Corporation holds 10 contracts worth $1.6M with Office of General Services - Design & Construction; none active today. The first started in 2010.

Total contract value
$1.6M
Current contract amounts
Spent to date
$1.2M
74% of contract value
Active contracts
0
None active today
Contracts on record
10
Since 2010
Agencies served
1
Most with Office of General Services - Design & Construction
Years active
16
First contract 2010

Contact & company

Business information and how to reach the company.

Company details for Air-Mechanical Corporation haven't been confirmed yet. If this is your company, claim the profile to add your website, address and contacts.

Contracts

10 contracts with New York State agencies, active first. Open a row for the full record.

Contracts
DetailsContractTypeContract no.Term

Correct failed mechanical system-BLDG 2 ward 400 south beach PC

DEB879HConstruction: Building

Office of General Services - Design & ConstructionConstruction: BuildingConstructionDEB879HApr 11, 2012to Aug 28, 2012Apr 11, 2012Aug 28, 2012$293,632$285,877 spent$285,877

Correct failed steam line building #103 manhattan PC

DEB825HConstruction: Building

Office of General Services - Design & ConstructionConstruction: BuildingConstructionDEB825HJan 20, 2012to May 19, 2012Jan 20, 2012May 19, 2012$75,000$19,296 spent$19,296

Restore failed steam supply BLDG 106 manhattan PC

DEB808HConstruction: Building

Office of General Services - Design & ConstructionConstruction: BuildingConstructionDEB808HJan 9, 2012to May 9, 2012Jan 9, 2012May 9, 2012$75,000$17,936 spent$17,936

Replace failed HVAC electrical equipment bronx PC

DEB796HConstruction: Building

Office of General Services - Design & ConstructionConstruction: BuildingConstructionDEB796HDec 30, 2011to Oct 9, 2012Dec 30, 2011Oct 9, 2012$200,000$88,542 spent$88,542

Decommission heating system arthur kill CF

DEB785HConstruction: Building

Office of General Services - Design & ConstructionConstruction: BuildingConstructionDEB785HDec 8, 2011to Nov 8, 2012Dec 8, 2011Nov 8, 2012$300,000$190,888 spent$190,888

Correct basement condensation problem building 144 rockland PC

DM2836HConstruction: Building

Office of General Services - Design & ConstructionConstruction: BuildingConstructionDM2836HOct 15, 2010to Jul 13, 2012Oct 15, 2010Jul 13, 2012$183,600$181,060 spent$181,060

Repair failed rooftop chiller units ST albans veterans home

DEB262HConstruction: Building

Office of General Services - Design & ConstructionConstruction: BuildingConstructionDEB262HJul 13, 2010to Nov 10, 2010Jul 13, 2010Nov 10, 2010$250,000$215,282 spent$215,282

Restore defective freezer BLDG 144 cook chill production center

DEB254HConstruction: Miscellaneous

Office of General Services - Design & ConstructionConstruction: MiscellaneousConstructionDEB254HJul 6, 2010to Dec 31, 2010Jul 6, 2010Dec 31, 2010$75,000$47,064 spent$47,064

Reconstruct ruptured domestic hot water line bronx PC

DEB243HConstruction: Building

Office of General Services - Design & ConstructionConstruction: BuildingConstructionDEB243HJun 28, 2010to Mar 31, 2011Jun 28, 2010Mar 31, 2011$80,000$79,753 spent$79,753

Replace roof, heating plant-BLDG 52 sing sing CF

DM2847HConstruction: Building

Office of General Services - Design & ConstructionConstruction: BuildingConstructionDM2847HJan 14, 2010to Apr 28, 2011Jan 14, 2010Apr 28, 2011$50,000$46,776 spent$46,776
Correct failed mechanical system-BLDG 2 ward 400 south beach PCOffice of General Services - Design & ConstructionApr 11, 2012 – Aug 28, 2012$293,632
Description
Correct failed mechanical system-BLDG 2 ward 400 south beach PC
Contract number
DEB879H
Type
Construction: BuildingConstruction
Term
Apr 11, 2012 → Aug 28, 20125 months
Approved
Jun 26, 2012
Status
Ended
Amount
$293,632
Spent to date
$285,877 · 97% of the amount
Correct failed steam line building #103 manhattan PCOffice of General Services - Design & ConstructionJan 20, 2012 – May 19, 2012$75,000
Description
Correct failed steam line building #103 manhattan PC
Contract number
DEB825H
Type
Construction: BuildingConstruction
Term
Jan 20, 2012 → May 19, 20124 months
Approved
Feb 16, 2012
Status
Ended
Amount
$75,000
Spent to date
$19,296 · 26% of the amount
Restore failed steam supply BLDG 106 manhattan PCOffice of General Services - Design & ConstructionJan 9, 2012 – May 9, 2012$75,000
Description
Restore failed steam supply BLDG 106 manhattan PC
Contract number
DEB808H
Type
Construction: BuildingConstruction
Term
Jan 9, 2012 → May 9, 20124 months
Approved
Feb 15, 2012
Status
Ended
Amount
$75,000
Spent to date
$17,936 · 24% of the amount
Replace failed HVAC electrical equipment bronx PCOffice of General Services - Design & ConstructionDec 30, 2011 – Oct 9, 2012$200,000
Description
Replace failed HVAC electrical equipment bronx PC
Contract number
DEB796H
Type
Construction: BuildingConstruction
Term
Dec 30, 2011 → Oct 9, 20129 months
Approved
Feb 1, 2012
Status
Ended
Amount
$200,000
Spent to date
$88,542 · 44% of the amount
Decommission heating system arthur kill CFOffice of General Services - Design & ConstructionDec 8, 2011 – Nov 8, 2012$300,000
Description
Decommission heating system arthur kill CF
Contract number
DEB785H
Type
Construction: BuildingConstruction
Term
Dec 8, 2011 → Nov 8, 201211 months
Approved
Jan 20, 2012
Status
Ended
Amount
$300,000
Spent to date
$190,888 · 64% of the amount
Correct basement condensation problem building 144 rockland PCOffice of General Services - Design & ConstructionOct 15, 2010 – Jul 13, 2012$183,600
Description
Correct basement condensation problem building 144 rockland PC
Contract number
DM2836H
Type
Construction: BuildingConstruction
Term
Oct 15, 2010 → Jul 13, 20121.8 years
Approved
Oct 15, 2010
Status
Ended
Amount
$183,600
Spent to date
$181,060 · 99% of the amount
Repair failed rooftop chiller units ST albans veterans homeOffice of General Services - Design & ConstructionJul 13, 2010 – Nov 10, 2010$250,000
Description
Repair failed rooftop chiller units ST albans veterans home
Contract number
DEB262H
Type
Construction: BuildingConstruction
Term
Jul 13, 2010 → Nov 10, 20104 months
Approved
Aug 16, 2010
Status
Ended
Amount
$250,000
Spent to date
$215,282 · 86% of the amount
Restore defective freezer BLDG 144 cook chill production centerOffice of General Services - Design & ConstructionJul 6, 2010 – Dec 31, 2010$75,000
Description
Restore defective freezer BLDG 144 cook chill production center
Contract number
DEB254H
Type
Construction: MiscellaneousConstruction
Term
Jul 6, 2010 → Dec 31, 20106 months
Approved
Nov 3, 2010
Status
Ended
Amount
$75,000
Spent to date
$47,064 · 63% of the amount
Reconstruct ruptured domestic hot water line bronx PCOffice of General Services - Design & ConstructionJun 28, 2010 – Mar 31, 2011$80,000
Description
Reconstruct ruptured domestic hot water line bronx PC
Contract number
DEB243H
Type
Construction: BuildingConstruction
Term
Jun 28, 2010 → Mar 31, 20119 months
Approved
Feb 7, 2011
Status
Ended
Amount
$80,000
Spent to date
$79,753 · 100% of the amount
Replace roof, heating plant-BLDG 52 sing sing CFOffice of General Services - Design & ConstructionJan 14, 2010 – Apr 28, 2011$50,000
Description
Replace roof, heating plant-BLDG 52 sing sing CF
Contract number
DM2847H
Type
Construction: BuildingConstruction
Term
Jan 14, 2010 → Apr 28, 201115 months
Approved
Sep 15, 2010
Status
Ended
Amount
$50,000
Spent to date
$46,776 · 94% of the amount
1–10 of 10

Contract-type mix

Share of contract value by type

  • Construction10 contracts$1.6M

Contracts over time

Contracts started per year

View as table
YearContracts
2010: 5 contracts, $638.6K5
2011: 2 contracts, $500.0K2
2012: 3 contracts, $443.6K3
2013: 0 contracts, $0.00
2014: 0 contracts, $0.00
2015: 0 contracts, $0.00
2016: 0 contracts, $0.00
2017: 0 contracts, $0.00
2018: 0 contracts, $0.00
2019: 0 contracts, $0.00
2020: 0 contracts, $0.00
2021: 0 contracts, $0.00
2022: 0 contracts, $0.00
2023: 0 contracts, $0.00
2024: 0 contracts, $0.00
2025: 0 contracts, $0.00
2026: 0 contracts, $0.00

How the Contractor Score adds up

Moderate (C, 56/100): two contract types, $1.6M in contracts; but no contract since 2012.

  • Contract volume+4.3measured

    $1.6M in current contract value across 10 contracts, more than 68% of scored contractors.

  • Recent activity−4.4measured

    No active contracts today; the most recent was approved in June 2012.

  • Agency breadth0.0measured

    Contracts with one state agency or facility.

  • Experience+1.5measured

    First contract started in January 2010 (16 years of contract history).

  • Contract-type mix+5.2measured

    2 contract types; the largest group is construction (100% of value). Goods and services contracts are 100% of the total.

  • Spending vs. value−0.5measured

    On 10 completed contracts with spending recorded, spending is 74% of the contract value. Spending below the full value is common (work can finish under budget) and isn't treated as a problem.

  • Federal award history0.0unknown

    No federal award history found. Scored as neutral.

  • Federal registration0.0unknown

    No federal contractor registration found. Scored as neutral.

50 + contributions = 56 (C, Moderate)Starts at 50. Bars: cool adds, warm subtracts.

Agencies served

Contract value with each agency or facility

Browse more

Contract figures are public New York State contract records as of Nov 13, 2026: current contract amounts and spending to date as reported. Company details are shown when we can match this contractor to a registered business with confidence.

RFP Detector is an independent service and is not affiliated with any government agency. Scores are informational.