Bagnall Electric Inc holds 14 contracts worth $1.2M with 4 New York State agencies, most with Office of General Services - Design & Construction; none active today. The first started in 2013.
- Total contract value
- $1.2M
- Current contract amounts
- Spent to date
- $755.4K
- 64% of contract value
- Active contracts
- 0
- None active today
- Contracts on record
- 14
- Since 2013
- Agencies served
- 4
- Most with Office of General Services - Design & Construction
- Years active
- 13
- First contract 2013
Contact & company
Business information and how to reach the company.
Contracts
14 contracts with New York State agencies, active first. Open a row for the full record.
| Details | Contract | Type | Contract no. | Term | |||||
|---|---|---|---|---|---|---|---|---|---|
Rogers Environ Education Center visitor center ADA improvements Sherburne Chenango county (E) D011817Construction: Building | Department of Environmental Conservation | Construction: BuildingConstruction | D011817 | Mar 25, 2021to Jan 21, 2022 | Mar 25, 2021 | Jan 21, 2022 | $52,705$50,323 spent | $50,323 | |
Provide salt storage buildings electrical Oneida & Morrisville Madison County Region 2 D47020EConstruction: Building | Office of General Services - Design & Construction | Construction: BuildingConstruction | D47020E | Mar 15, 2021to Jan 4, 2022 | Mar 15, 2021 | Jan 4, 2022 | $96,855$96,599 spent | $96,599 | |
Replace Failed Pumps Swiftwater & Flood Training Facility Oneida County DEE106EConstruction: Building | Office of General Services - Design & Construction | Construction: BuildingConstruction | DEE106E | May 24, 2019to Nov 20, 2019 | May 24, 2019 | Nov 20, 2019 | $200,000$3,817 spent | $3,817 | |
Upgrade Data Closet B39 Operating Temperature Central NY PC Oneida County DM3088EConstruction: Building | Office of General Services - Design & Construction | Construction: BuildingConstruction | DM3088E | Oct 1, 2018to Aug 14, 2019 | Oct 1, 2018 | Aug 14, 2019 | $96,581$96,322 spent | $96,322 | |
Restore Failed Generator Central NY PC Oneida County DED862EConstruction: Building | Office of General Services - Design & Construction | Construction: BuildingConstruction | DED862E | Jul 13, 2018to Feb 1, 2019 | Jul 13, 2018 | Feb 1, 2019 | $250,000$111,221 spent | $111,221 | |
Provide Salt Storage Building Oneida County DOT Region 2 (E) D45844EConstruction: Building | Office of General Services - Design & Construction | Construction: BuildingConstruction | D45844E | Jul 12, 2018to Dec 30, 2018 | Jul 12, 2018 | Dec 30, 2018 | $27,330$24,930 spent | $24,930 | |
Guard Shack and Pavilion Renovations OP200423Service: Building services | Central New York Psychiatric Center | Service: Building servicesService | OP200423 | Apr 1, 2018to Sep 30, 2018 | Apr 1, 2018 | Sep 30, 2018 | $104,936$104,936 spent | $104,936 | |
New contract, Replace windows, Bldgs 3&22, Mid State CF, Marcy NY. D44715EConstruction: Miscellaneous | Office of General Services - Design & Construction | Construction: MiscellaneousConstruction | D44715E | May 6, 2016to May 18, 2018 | May 6, 2016 | May 18, 2018 | $59,230$55,979 spent | $55,979 | |
Provide heating boilers, taberg residential center for girls D44989EConstruction: Building | Office of General Services - Design & Construction | Construction: BuildingConstruction | D44989E | Aug 10, 2015to Nov 2, 2016 | Aug 10, 2015 | Nov 2, 2016 | $38,794$36,128 spent | $36,128 | |
Demolish buildings 3 & 70, mohawk valley PC, utica NY D44877EConstruction: Building | Office of General Services - Design & Construction | Construction: BuildingConstruction | D44877E | May 20, 2015to Dec 16, 2015 | May 20, 2015 | Dec 16, 2015 | $36,850$34,850 spent | $34,850 | |
Rehab elevators, Forensic side Bldg. 39, Central NY PC (E) D44866EConstruction: Building | Office of General Services - Design & Construction | Construction: BuildingConstruction | D44866E | May 15, 2015to Sep 16, 2016 | May 15, 2015 | Sep 16, 2016 | $49,313$49,309 spent | $49,309 | |
Correct failed electric feeder building 64 mohawk valley PC 1400 noyes street utica oneida county DEC773EConstruction: Building | Office of General Services - Design & Construction | Construction: BuildingConstruction | DEC773E | Nov 10, 2014to Mar 10, 2015 | Nov 10, 2014 | Mar 10, 2015 | $75,000$8,041 spent | $8,041 | |
Preventive Maintenance - Gener T000222Contract not subject to state pre-audit | Mohawk Valley Psychiatric Center | Contract not subject to state pre-auditNot pre-audited | T000222 | Sep 1, 2013to Aug 31, 2016 | Sep 1, 2013 | Aug 31, 2016 | $2,400$1,400 spent | $1,400 | |
Remove/Replace Heating System @ Region 2 Oneida D44526EConstruction: Building | Office of General Services - Design & Construction | Construction: BuildingConstruction | D44526E | Jul 31, 2013to Dec 3, 2014 | Jul 31, 2013 | Dec 3, 2014 | $82,784$81,548 spent | $81,548 |
Rogers Environ Education Center visitor center ADA improvements Sherburne Chenango county (E)Department of Environmental ConservationMar 25, 2021 – Jan 21, 2022$52,705
- Description
- Rogers Environ Education Center visitor center ADA improvements Sherburne Chenango county (E)
- Contract number
- D011817
- Type
- Construction: BuildingConstruction
- Term
- Mar 25, 2021 → Jan 21, 202210 months
- Approved
- Mar 25, 2021
- Status
- Ended
- Amount
- $52,705
- Spent to date
- $50,323 · 95% of the amount
Provide salt storage buildings electrical Oneida & Morrisville Madison County Region 2Office of General Services - Design & ConstructionMar 15, 2021 – Jan 4, 2022$96,855
- Description
- Provide salt storage buildings electrical Oneida & Morrisville Madison County Region 2
- Contract number
- D47020E
- Type
- Construction: BuildingConstruction
- Term
- Mar 15, 2021 → Jan 4, 202210 months
- Approved
- Mar 15, 2021
- Status
- Ended
- Amount
- $96,855
- Spent to date
- $96,599 · 100% of the amount
Replace Failed Pumps Swiftwater & Flood Training Facility Oneida CountyOffice of General Services - Design & ConstructionMay 24, 2019 – Nov 20, 2019$200,000
- Description
- Replace Failed Pumps Swiftwater & Flood Training Facility Oneida County
- Contract number
- DEE106E
- Type
- Construction: BuildingConstruction
- Term
- May 24, 2019 → Nov 20, 20196 months
- Approved
- Feb 18, 2020
- Status
- Ended
- Amount
- $200,000
- Spent to date
- $3,817 · 2% of the amount
Upgrade Data Closet B39 Operating Temperature Central NY PC Oneida CountyOffice of General Services - Design & ConstructionOct 1, 2018 – Aug 14, 2019$96,581
- Description
- Upgrade Data Closet B39 Operating Temperature Central NY PC Oneida County
- Contract number
- DM3088E
- Type
- Construction: BuildingConstruction
- Term
- Oct 1, 2018 → Aug 14, 201910 months
- Approved
- Oct 1, 2018
- Status
- Ended
- Amount
- $96,581
- Spent to date
- $96,322 · 100% of the amount
Restore Failed Generator Central NY PC Oneida CountyOffice of General Services - Design & ConstructionJul 13, 2018 – Feb 1, 2019$250,000
- Description
- Restore Failed Generator Central NY PC Oneida County
- Contract number
- DED862E
- Type
- Construction: BuildingConstruction
- Term
- Jul 13, 2018 → Feb 1, 20197 months
- Approved
- Sep 4, 2018
- Status
- Ended
- Amount
- $250,000
- Spent to date
- $111,221 · 44% of the amount
Provide Salt Storage Building Oneida County DOT Region 2 (E)Office of General Services - Design & ConstructionJul 12, 2018 – Dec 30, 2018$27,330
- Description
- Provide Salt Storage Building Oneida County DOT Region 2 (E)
- Contract number
- D45844E
- Type
- Construction: BuildingConstruction
- Term
- Jul 12, 2018 → Dec 30, 20186 months
- Approved
- Jul 12, 2018
- Status
- Ended
- Amount
- $27,330
- Spent to date
- $24,930 · 91% of the amount
Guard Shack and Pavilion RenovationsCentral New York Psychiatric CenterApr 1, 2018 – Sep 30, 2018$104,936
- Description
- Guard Shack and Pavilion Renovations
- Contract number
- OP200423
- Type
- Service: Building servicesService
- Term
- Apr 1, 2018 → Sep 30, 20186 months
- Approved
- May 22, 2018
- Status
- Ended
- Amount
- $104,936
- Spent to date
- $104,936 · 100% of the amount
New contract, Replace windows, Bldgs 3&22, Mid State CF, Marcy NY.Office of General Services - Design & ConstructionMay 6, 2016 – May 18, 2018$59,230
- Description
- New contract, Replace windows, Bldgs 3&22, Mid State CF, Marcy NY.
- Contract number
- D44715E
- Type
- Construction: MiscellaneousConstruction
- Term
- May 6, 2016 → May 18, 20182 years
- Approved
- May 6, 2016
- Status
- Ended
- Amount
- $59,230
- Spent to date
- $55,979 · 95% of the amount
Provide heating boilers, taberg residential center for girlsOffice of General Services - Design & ConstructionAug 10, 2015 – Nov 2, 2016$38,794
- Description
- Provide heating boilers, taberg residential center for girls
- Contract number
- D44989E
- Type
- Construction: BuildingConstruction
- Term
- Aug 10, 2015 → Nov 2, 201615 months
- Approved
- Aug 10, 2015
- Status
- Ended
- Amount
- $38,794
- Spent to date
- $36,128 · 93% of the amount
Demolish buildings 3 & 70, mohawk valley PC, utica NYOffice of General Services - Design & ConstructionMay 20, 2015 – Dec 16, 2015$36,850
- Description
- Demolish buildings 3 & 70, mohawk valley PC, utica NY
- Contract number
- D44877E
- Type
- Construction: BuildingConstruction
- Term
- May 20, 2015 → Dec 16, 20157 months
- Approved
- May 20, 2015
- Status
- Ended
- Amount
- $36,850
- Spent to date
- $34,850 · 95% of the amount
Rehab elevators, Forensic side Bldg. 39, Central NY PC (E)Office of General Services - Design & ConstructionMay 15, 2015 – Sep 16, 2016$49,313
- Description
- Rehab elevators, Forensic side Bldg. 39, Central NY PC (E)
- Contract number
- D44866E
- Type
- Construction: BuildingConstruction
- Term
- May 15, 2015 → Sep 16, 201616 months
- Approved
- May 15, 2015
- Status
- Ended
- Amount
- $49,313
- Spent to date
- $49,309 · 100% of the amount
Correct failed electric feeder building 64 mohawk valley PC 1400 noyes street utica oneida countyOffice of General Services - Design & ConstructionNov 10, 2014 – Mar 10, 2015$75,000
- Description
- Correct failed electric feeder building 64 mohawk valley PC 1400 noyes street utica oneida county
- Contract number
- DEC773E
- Type
- Construction: BuildingConstruction
- Term
- Nov 10, 2014 → Mar 10, 20154 months
- Approved
- Nov 25, 2014
- Status
- Ended
- Amount
- $75,000
- Spent to date
- $8,041 · 11% of the amount
Preventive Maintenance - GenerMohawk Valley Psychiatric CenterSep 1, 2013 – Aug 31, 2016$2,400
- Description
- Preventive Maintenance - Gener
- Contract number
- T000222
- Type
- Contract not subject to state pre-auditNot pre-audited
- Term
- Sep 1, 2013 → Aug 31, 20163 years
- Approved
- Oct 2, 2013
- Status
- Ended
- Amount
- $2,400
- Spent to date
- $1,400 · 58% of the amount
Remove/Replace Heating System @ Region 2 OneidaOffice of General Services - Design & ConstructionJul 31, 2013 – Dec 3, 2014$82,784
- Description
- Remove/Replace Heating System @ Region 2 Oneida
- Contract number
- D44526E
- Type
- Construction: BuildingConstruction
- Term
- Jul 31, 2013 → Dec 3, 201416 months
- Approved
- Jul 31, 2013
- Status
- Ended
- Amount
- $82,784
- Spent to date
- $81,548 · 99% of the amount
Contract-type mix
Share of contract value by type
- Construction12 contracts$1.1M
- Service: Building services1 contract$104.9K
- Contract not subject to state pre-audit1 contract$2.4K
Contracts over time
Contracts started per year
View as table
| Year | Contracts |
|---|---|
| 2013: 2 contracts, $85.2K | 2 |
| 2014: 1 contracts, $75.0K | 1 |
| 2015: 3 contracts, $125.0K | 3 |
| 2016: 1 contracts, $59.2K | 1 |
| 2017: 0 contracts, $0.0 | 0 |
| 2018: 4 contracts, $478.8K | 4 |
| 2019: 1 contracts, $200.0K | 1 |
| 2020: 0 contracts, $0.0 | 0 |
| 2021: 2 contracts, $149.6K | 2 |
| 2022: 0 contracts, $0.0 | 0 |
| 2023: 0 contracts, $0.0 | 0 |
| 2024: 0 contracts, $0.0 | 0 |
| 2025: 0 contracts, $0.0 | 0 |
| 2026: 0 contracts, $0.0 | 0 |
How the Contractor Score adds up
Established (B, 67/100): works with 4 agencies, mix of 4 contract types.
- Contract volume+3.3measured
$1.2M in current contract value across 14 contracts, more than 64% of scored contractors.
- Recent activity−1.2measured
No active contracts today; the most recent was approved in March 2021.
- Agency breadth+8.3measured
Contracts with 4 different state agencies and facilities.
- Experience+0.1measured
First contract started in July 2013 (13 years of contract history).
- Contract-type mix+6.9measured
4 contract types; the largest group is construction (91% of value). Goods and services contracts are 100% of the total.
- Spending vs. value−0.8measured
On 14 completed contracts with spending recorded, spending is 64% of the contract value. Spending below the full value is common (work can finish under budget) and isn't treated as a problem.
- Federal award history0.0unknown
No federal award history found. Scored as neutral.
- Federal registration0.0unknown
No federal contractor registration found. Scored as neutral.
50 + contributions = 67 (B, Established)Starts at 50. Bars: cool adds, warm subtracts.
Agencies served
Contract value with each agency or facility
Similar contractors
- A
Oconnell Electric Company Inc
Victor, NYConstruction & Renovation
Since 200052 agencies
- Contract value
- $251.8M
- Contracts
- 220
- Active
- 13
- B
Eastern Building & Restoration Inc
Construction & Renovation
Since 20074 agencies
- Contract value
- $19.1M
- Contracts
- 24
- Active
- 0
- A
Betlem Service Corp
Rochester, NYConstruction & Renovation
Since 200818 agencies
- Contract value
- $32.8M
- Contracts
- 58
- Active
- 15
- B
Northern Pioneer Contractors Inc
Construction & Renovation
Since 20163 agencies
- Contract value
- $1.2M
- Contracts
- 7
- Active
- 1
- B
Eventus Construction Co Inc
Construction & Renovation
Since 20123 agencies
- Contract value
- $1.1M
- Contracts
- 4
- Active
- 0
- C
Arcon Construction & Management Services Inc
Construction & Renovation
Since 20114 agencies
- Contract value
- $1.6M
- Contracts
- 5
- Active
- 0
- More construction & renovation contractors Ranked by contract value
Browse more
- Office of General Services - Design & Construction contractors
- Central New York Psychiatric Center contractors
- Department of Environmental Conservation contractors
- Mohawk Valley Psychiatric Center contractors
- Construction & Renovation contractors
- Top contractors
- All contractors
Contract figures are public New York State contract records as of Nov 13, 2026: current contract amounts and spending to date as reported. Company details are shown when we can match this contractor to a registered business with confidence.
RFP Detector is an independent service and is not affiliated with any government agency. Scores are informational.