Skip to content
NY State contractorConstruction & Renovation

Binghamton Road Electric LLC

Binghamton, NY State contracts since 2011Updated Nov 13, 2026

Binghamton Road Electric LLC holds 24 contracts worth $38.1M with 2 New York State agencies, most with Department of Transportation; 1 active today. The first started in 2011.

Total contract value
$38.1M
Current contract amounts
Spent to date
$36.6M
96% of contract value
Active contracts
1
$4.6M in active value
Contracts on record
24
Since 2011
Agencies served
2
Most with Department of Transportation
Years active
15
First contract 2011

Contact & company

Business information and how to reach the company.

Email

Address

170 E Service HwyBinghamton, NY 13901Broome County
Legal name
Binghamton Road Electric, LLC
Identifiers
UEI RYFJDCRMJF33 · CAGE 6HVM3
Federal registration
Active · renews by Mar 2027
In business since
2008

Industry codes (NAICS)

  • 238210Electrical Contractors and Other Wiring Installation Contractors

Leadership

  • Vaughn Ellsworth

    Member

  • Jennifer Ellsworth

    Member

Contracts

24 contracts with New York State agencies, active first. Open a row for the full record.

Contracts
DetailsContractTypeContract no.Term

Regional Traffic Signal Project Region 3 Cayuga Cortland Onondaga Oswego Seneca & Tompkins Counties

D265171Construction: Standby contractsActive

Department of TransportationConstruction: Standby contractsConstructionD265171Feb 21, 2024to Jun 15, 2027Feb 21, 2024Jun 15, 2027$4,623,147$3,563,929 spent$3,563,929

Signal replacements on NY Route 17C & 26 in Village of Endicott & Town of Union in Broome County

D265156Construction: Highway

Department of TransportationConstruction: HighwayConstructionD265156Jun 18, 2024to Jul 31, 2026Jun 18, 2024Jul 31, 2026$2,427,714$2,215,150 spent$2,215,150

Signal improvement for Clinton Jefferson Lewis & St. Lawrence Counties in Region 7

D265107Construction: Highway

Department of TransportationConstruction: HighwayConstructionD265107Dec 7, 2023to May 15, 2026Dec 7, 2023May 15, 2026$1,672,013$1,668,040 spent$1,668,040

Signal Replacement on NY Rtes 14 & 415 in Elmira Heights Horseheads & Riverside Chemung Steuben Cos

D265113Construction: Highway

Department of TransportationConstruction: HighwayConstructionD265113Dec 6, 2023to Dec 12, 2025Dec 6, 2023Dec 12, 2025$1,078,467$1,078,467 spent$1,078,467

Region 3 traffic signal project Cayuga Cortland Onondaga Oswego Seneca Tompkins Counties

D264844Construction: Standby contracts

Department of TransportationConstruction: Standby contractsConstructionD264844Aug 29, 2022to Aug 28, 2026Aug 29, 2022Aug 28, 2026$3,144,255$2,929,143 spent$2,929,143

Pedestrian safety improvements route 11 Malone Franklin county

D264438Construction: Highway

Department of TransportationConstruction: HighwayConstructionD264438Apr 30, 2021to Jun 15, 2022Apr 30, 2021Jun 15, 2022$3,138,043$3,138,043 spent$3,138,043

Route 11 & 434 upgrade pedestrian accommodations Chenango & Vestal Broome County

D264436Construction: Highway

Department of TransportationConstruction: HighwayConstructionD264436Apr 16, 2021to Dec 31, 2021Apr 16, 2021Dec 31, 2021$530,379$530,379 spent$530,379

Pedestrian Safety Action Plan Signalized Intersections Poughkeepsie Red Hook Dutchess County

D264056Construction: Highway

Department of TransportationConstruction: HighwayConstructionD264056Nov 15, 2019to Feb 28, 2021Nov 15, 2019Feb 28, 2021$3,331,797$3,331,797 spent$3,331,797

Pedestrian Safety Improvements Region 9 All Counties

D264007Construction: Highway

Department of TransportationConstruction: HighwayConstructionD264007Oct 25, 2019to Nov 29, 2020Oct 25, 2019Nov 29, 2020$590,346$590,346 spent$590,346

Install Low Bridge Warning System on the Hutchinson River Pkwy. Westchester County

D263838Construction: Highway

Department of TransportationConstruction: HighwayConstructionD263838Nov 27, 2018to Aug 31, 2019Nov 27, 2018Aug 31, 2019$1,978,446$1,978,446 spent$1,978,446

Electrical System Improvements Lake Eaton Campground Hamilton County

D011214Construction: Building

Department of Environmental ConservationConstruction: BuildingConstructionD011214Oct 15, 2018to Jul 9, 2019Oct 15, 2018Jul 9, 2019$442,808$442,808 spent$442,808

Ped safety plan, Phase 1, various loc, Broome Chenango, Delaware, Otsego Counties

D263502Construction: Standby contracts

Department of TransportationConstruction: Standby contractsConstructionD263502Aug 9, 2017to Jul 31, 2020Aug 9, 2017Jul 31, 2020$3,036,126$3,036,126 spent$3,036,126

Traffic signal requirements, Tioga, Broome, Otsego County

D263407Construction: Standby contracts

Department of TransportationConstruction: Standby contractsConstructionD263407Aug 7, 2017to Dec 8, 2019Aug 7, 2017Dec 8, 2019$823,551$823,551 spent$823,551

Reconstruction of Curb Ramps/Sidewalks/Pedestrian Signals @Var Locations Cattaraugus & Chautauqua Co

D263456Construction: Highway

Department of TransportationConstruction: HighwayConstructionD263456May 12, 2017to Dec 30, 2017May 12, 2017Dec 30, 2017$911,006$911,006 spent$911,006

Safe Routes to School Pedestrian Improvements Schoharie, Otsego Counties

D263312Construction: Highway

Department of TransportationConstruction: HighwayConstructionD263312Mar 21, 2017to Aug 31, 2017Mar 21, 2017Aug 31, 2017$418,685$418,685 spent$418,685

ADA Compliance, Curb Ramps, Sidewalks, Pedestrian Signal Install, Various Routes, Region 5

D263159Construction: Highway

Department of TransportationConstruction: HighwayConstructionD263159May 11, 2016to Dec 30, 2016May 11, 2016Dec 30, 2016$961,428$961,428 spent$961,428

Traffic signal improvements at4 intersctn, towns of carmel, bedford, hamlet of armonk

D262776Construction: Highway

Department of TransportationConstruction: HighwayConstructionD262776Mar 12, 2015to Jun 18, 2016Mar 12, 2015Jun 18, 2016$928,074$928,074 spent$928,074

Traffic & pedestrian light signal installations various locations region 9

D262670Construction: Highway

Department of TransportationConstruction: HighwayConstructionD262670Sep 23, 2014to Mar 31, 2016Sep 23, 2014Mar 31, 2016$872,629$872,629 spent$872,629

Install of overheight vehicle detection systems various entrance ramps hutchinson river parkway

D262581Construction: Highway

Department of TransportationConstruction: HighwayConstructionD262581Apr 17, 2014to Apr 15, 2016Apr 17, 2014Apr 15, 2016$1,507,554$1,507,554 spent$1,507,554

New countdown pedestrian crossing signals region 4

D262435Construction: Highway

Department of TransportationConstruction: HighwayConstructionD262435Dec 23, 2013to Jan 30, 2015Dec 23, 2013Jan 30, 2015$1,417,612$1,417,612 spent$1,417,612
Regional Traffic Signal Project Region 3 Cayuga Cortland Onondaga Oswego Seneca & Tompkins CountiesDepartment of TransportationFeb 21, 2024 – Jun 15, 2027Active$4,623,147
Description
Regional Traffic Signal Project Region 3 Cayuga Cortland Onondaga Oswego Seneca & Tompkins Counties
Contract number
D265171
Type
Construction: Standby contractsConstruction
Term
Feb 21, 2024 → Jun 15, 20273.3 years
Approved
Feb 21, 2024
Status
Active
Amount
$4,623,147
Spent to date
$3,563,929 · 77% of the amount
Signal replacements on NY Route 17C & 26 in Village of Endicott & Town of Union in Broome CountyDepartment of TransportationJun 18, 2024 – Jul 31, 2026$2,427,714
Description
Signal replacements on NY Route 17C & 26 in Village of Endicott & Town of Union in Broome County
Contract number
D265156
Type
Construction: HighwayConstruction
Term
Jun 18, 2024 → Jul 31, 20262.1 years
Approved
Jun 18, 2024
Status
Ended
Amount
$2,427,714
Spent to date
$2,215,150 · 91% of the amount
Signal improvement for Clinton Jefferson Lewis & St. Lawrence Counties in Region 7Department of TransportationDec 7, 2023 – May 15, 2026$1,672,013
Description
Signal improvement for Clinton Jefferson Lewis & St. Lawrence Counties in Region 7
Contract number
D265107
Type
Construction: HighwayConstruction
Term
Dec 7, 2023 → May 15, 20262.4 years
Approved
Dec 7, 2023
Status
Ended
Amount
$1,672,013
Spent to date
$1,668,040 · 100% of the amount
Signal Replacement on NY Rtes 14 & 415 in Elmira Heights Horseheads & Riverside Chemung Steuben CosDepartment of TransportationDec 6, 2023 – Dec 12, 2025$1,078,467
Description
Signal Replacement on NY Rtes 14 & 415 in Elmira Heights Horseheads & Riverside Chemung Steuben Cos
Contract number
D265113
Type
Construction: HighwayConstruction
Term
Dec 6, 2023 → Dec 12, 20252 years
Approved
Dec 6, 2023
Status
Ended
Amount
$1,078,467
Spent to date
$1,078,467 · 100% of the amount
Region 3 traffic signal project Cayuga Cortland Onondaga Oswego Seneca Tompkins CountiesDepartment of TransportationAug 29, 2022 – Aug 28, 2026$3,144,255
Description
Region 3 traffic signal project Cayuga Cortland Onondaga Oswego Seneca Tompkins Counties
Contract number
D264844
Type
Construction: Standby contractsConstruction
Term
Aug 29, 2022 → Aug 28, 20264 years
Approved
Aug 29, 2022
Status
Ended
Amount
$3,144,255
Spent to date
$2,929,143 · 93% of the amount
Pedestrian safety improvements route 11 Malone Franklin countyDepartment of TransportationApr 30, 2021 – Jun 15, 2022$3,138,043
Description
Pedestrian safety improvements route 11 Malone Franklin county
Contract number
D264438
Type
Construction: HighwayConstruction
Term
Apr 30, 2021 → Jun 15, 202214 months
Approved
Apr 30, 2021
Status
Ended
Amount
$3,138,043
Spent to date
$3,138,043 · 100% of the amount
Route 11 & 434 upgrade pedestrian accommodations Chenango & Vestal Broome CountyDepartment of TransportationApr 16, 2021 – Dec 31, 2021$530,379
Description
Route 11 & 434 upgrade pedestrian accommodations Chenango & Vestal Broome County
Contract number
D264436
Type
Construction: HighwayConstruction
Term
Apr 16, 2021 → Dec 31, 20219 months
Approved
Apr 16, 2021
Status
Ended
Amount
$530,379
Spent to date
$530,379 · 100% of the amount
Pedestrian Safety Action Plan Signalized Intersections Poughkeepsie Red Hook Dutchess CountyDepartment of TransportationNov 15, 2019 – Feb 28, 2021$3,331,797
Description
Pedestrian Safety Action Plan Signalized Intersections Poughkeepsie Red Hook Dutchess County
Contract number
D264056
Type
Construction: HighwayConstruction
Term
Nov 15, 2019 → Feb 28, 202115 months
Approved
Nov 15, 2019
Status
Ended
Amount
$3,331,797
Spent to date
$3,331,797 · 100% of the amount
Pedestrian Safety Improvements Region 9 All CountiesDepartment of TransportationOct 25, 2019 – Nov 29, 2020$590,346
Description
Pedestrian Safety Improvements Region 9 All Counties
Contract number
D264007
Type
Construction: HighwayConstruction
Term
Oct 25, 2019 → Nov 29, 202013 months
Approved
Oct 25, 2019
Status
Ended
Amount
$590,346
Spent to date
$590,346 · 100% of the amount
Install Low Bridge Warning System on the Hutchinson River Pkwy. Westchester CountyDepartment of TransportationNov 27, 2018 – Aug 31, 2019$1,978,446
Description
Install Low Bridge Warning System on the Hutchinson River Pkwy. Westchester County
Contract number
D263838
Type
Construction: HighwayConstruction
Term
Nov 27, 2018 → Aug 31, 20199 months
Approved
Nov 27, 2018
Status
Ended
Amount
$1,978,446
Spent to date
$1,978,446 · 100% of the amount
Electrical System Improvements Lake Eaton Campground Hamilton CountyDepartment of Environmental ConservationOct 15, 2018 – Jul 9, 2019$442,808
Description
Electrical System Improvements Lake Eaton Campground Hamilton County
Contract number
D011214
Type
Construction: BuildingConstruction
Term
Oct 15, 2018 → Jul 9, 20199 months
Approved
Oct 15, 2018
Status
Ended
Amount
$442,808
Spent to date
$442,808 · 100% of the amount
Ped safety plan, Phase 1, various loc, Broome Chenango, Delaware, Otsego CountiesDepartment of TransportationAug 9, 2017 – Jul 31, 2020$3,036,126
Description
Ped safety plan, Phase 1, various loc, Broome Chenango, Delaware, Otsego Counties
Contract number
D263502
Type
Construction: Standby contractsConstruction
Term
Aug 9, 2017 → Jul 31, 20203 years
Approved
Aug 9, 2017
Status
Ended
Amount
$3,036,126
Spent to date
$3,036,126 · 100% of the amount
Traffic signal requirements, Tioga, Broome, Otsego CountyDepartment of TransportationAug 7, 2017 – Dec 8, 2019$823,551
Description
Traffic signal requirements, Tioga, Broome, Otsego County
Contract number
D263407
Type
Construction: Standby contractsConstruction
Term
Aug 7, 2017 → Dec 8, 20192.3 years
Approved
Aug 7, 2017
Status
Ended
Amount
$823,551
Spent to date
$823,551 · 100% of the amount
Reconstruction of Curb Ramps/Sidewalks/Pedestrian Signals @Var Locations Cattaraugus & Chautauqua CoDepartment of TransportationMay 12, 2017 – Dec 30, 2017$911,006
Description
Reconstruction of Curb Ramps/Sidewalks/Pedestrian Signals @Var Locations Cattaraugus & Chautauqua Co
Contract number
D263456
Type
Construction: HighwayConstruction
Term
May 12, 2017 → Dec 30, 20178 months
Approved
May 12, 2017
Status
Ended
Amount
$911,006
Spent to date
$911,006 · 100% of the amount
Safe Routes to School Pedestrian Improvements Schoharie, Otsego CountiesDepartment of TransportationMar 21, 2017 – Aug 31, 2017$418,685
Description
Safe Routes to School Pedestrian Improvements Schoharie, Otsego Counties
Contract number
D263312
Type
Construction: HighwayConstruction
Term
Mar 21, 2017 → Aug 31, 20175 months
Approved
Mar 21, 2017
Status
Ended
Amount
$418,685
Spent to date
$418,685 · 100% of the amount
ADA Compliance, Curb Ramps, Sidewalks, Pedestrian Signal Install, Various Routes, Region 5Department of TransportationMay 11, 2016 – Dec 30, 2016$961,428
Description
ADA Compliance, Curb Ramps, Sidewalks, Pedestrian Signal Install, Various Routes, Region 5
Contract number
D263159
Type
Construction: HighwayConstruction
Term
May 11, 2016 → Dec 30, 20168 months
Approved
May 11, 2016
Status
Ended
Amount
$961,428
Spent to date
$961,428 · 100% of the amount
Traffic signal improvements at4 intersctn, towns of carmel, bedford, hamlet of armonkDepartment of TransportationMar 12, 2015 – Jun 18, 2016$928,074
Description
Traffic signal improvements at4 intersctn, towns of carmel, bedford, hamlet of armonk
Contract number
D262776
Type
Construction: HighwayConstruction
Term
Mar 12, 2015 → Jun 18, 201615 months
Approved
Mar 12, 2015
Status
Ended
Amount
$928,074
Spent to date
$928,074 · 100% of the amount
Traffic & pedestrian light signal installations various locations region 9Department of TransportationSep 23, 2014 – Mar 31, 2016$872,629
Description
Traffic & pedestrian light signal installations various locations region 9
Contract number
D262670
Type
Construction: HighwayConstruction
Term
Sep 23, 2014 → Mar 31, 20161.5 years
Approved
Sep 23, 2014
Status
Ended
Amount
$872,629
Spent to date
$872,629 · 100% of the amount
Install of overheight vehicle detection systems various entrance ramps hutchinson river parkwayDepartment of TransportationApr 17, 2014 – Apr 15, 2016$1,507,554
Description
Install of overheight vehicle detection systems various entrance ramps hutchinson river parkway
Contract number
D262581
Type
Construction: HighwayConstruction
Term
Apr 17, 2014 → Apr 15, 20162 years
Approved
Apr 17, 2014
Status
Ended
Amount
$1,507,554
Spent to date
$1,507,554 · 100% of the amount
New countdown pedestrian crossing signals region 4Department of TransportationDec 23, 2013 – Jan 30, 2015$1,417,612
Description
New countdown pedestrian crossing signals region 4
Contract number
D262435
Type
Construction: HighwayConstruction
Term
Dec 23, 2013 → Jan 30, 201513 months
Approved
Dec 23, 2013
Status
Ended
Amount
$1,417,612
Spent to date
$1,417,612 · 100% of the amount
1–20 of 24Page 1 of 2

Contract-type mix

Share of contract value by type

  • Construction24 contracts$38.1M

Contracts over time

Contracts started per year

View as table
YearContracts
2011: 1 contracts, $661.7K1
2012: 2 contracts, $748.8K2
2013: 2 contracts, $4.3M2
2014: 2 contracts, $2.4M2
2015: 1 contracts, $928.1K1
2016: 1 contracts, $961.4K1
2017: 4 contracts, $5.2M4
2018: 2 contracts, $2.4M2
2019: 2 contracts, $3.9M2
2020: 0 contracts, $0.00
2021: 2 contracts, $3.7M2
2022: 1 contracts, $3.1M1
2023: 2 contracts, $2.8M2
2024: 2 contracts, $7.1M2
2025: 0 contracts, $0.00
2026: 0 contracts, $0.00

How the Contractor Score adds up

Extensive (A, 91/100): $38M in contracts, 1 active contract.

  • Contract volume+14.6measured

    $38M in current contract value across 24 contracts, more than 93% of scored contractors.

  • Recent activity+9.2measured

    1 active contract today; the most recent was approved in June 2024.

  • Agency breadth+4.3measured

    Contracts with 2 different state agencies and facilities.

  • Experience+1.2measured

    First contract started in January 2011 (15 years of contract history).

  • Contract-type mix+6.4measured

    3 contract types; the largest group is construction (100% of value). Goods and services contracts are 100% of the total.

  • Spending vs. value+0.1measured

    On 23 completed contracts with spending recorded, spending is 99% of the contract value. Spending below the full value is common (work can finish under budget) and isn't treated as a problem.

  • Federal award history0.0unknown

    No federal award history found. Scored as neutral.

  • Federal registration+5.2measured

    Registered to do business with the federal government (registration active).

50 + contributions = 91 (A, Extensive)Starts at 50. Bars: cool adds, warm subtracts.

Agencies served

Contract value with each agency or facility

Browse more

Contract figures are public New York State contract records as of Nov 13, 2026: current contract amounts and spending to date as reported. Company details are shown when we can match this contractor to a registered business with confidence.

RFP Detector is an independent service and is not affiliated with any government agency. Scores are informational.