Frey Electric Construction Co Inc
ATonawanda, NY State contracts since 2007Updated Nov 13, 2026
Frey Electric Construction Co Inc holds 35 contracts worth $38.8M with 6 New York State agencies, most with Office of General Services - Design & Construction; 5 active today. The first started in 2007.
- Total contract value
- $38.8M
- Current contract amounts
- Spent to date
- $29.7M
- 76% of contract value
- Active contracts
- 5
- $2.8M in active value
- Contracts on record
- 35
- Since 2007
- Agencies served
- 6
- Most with Office of General Services - Design & Construction
- Years active
- 19
- First contract 2007
Contact & company
Business information and how to reach the company.
Phone
Address
- Legal name
- Frey Electric Construction Co. Inc.
- Identifiers
- UEI G9NJLS8N6R35 · CAGE 3N1R7
- Federal registration
- Active · renews by Jun 2027
- In business since
- 1950
Industry codes (NAICS)
- 238210Electrical Contractors and Other Wiring Installation Contractors
Leadership
Kent Frey
CEO
Jeff Avolio-Farr
Controller
Contracts
35 contracts with New York State agencies, active first. Open a row for the full record.
| Details | Contract | Type | Contract no. | Term | |||||
|---|---|---|---|---|---|---|---|---|---|
Falconwood roof replacement electrical work Beaver Island State Park Erie County D006528Construction: BuildingActive | Office of Parks Recreation & Historic Preservation | Construction: BuildingConstruction | D006528 | Jul 23, 2026to Apr 29, 2027 | Jul 23, 2026 | Apr 29, 2027 | $489,000$0 spent | $0 | |
Electrical work for lab renovation at Furnas Hall University at Buffalo in Erie County D000129Construction: BuildingActive | SUNY at Buffalo | Construction: BuildingConstruction | D000129 | May 15, 2026to Mar 30, 2028 | May 15, 2026 | Mar 30, 2028 | $780,000$110,104 spent | $110,104 | |
Electrical work for lodge roofing replacement at Woodlawn Beach State Park in Erie County D006529Construction: BuildingActive | Office of Parks Recreation & Historic Preservation | Construction: BuildingConstruction | D006529 | Apr 24, 2026to May 29, 2027 | Apr 24, 2026 | May 29, 2027 | $490,000$0 spent | $0 | |
Electrical to renovate special care and oral facial pain clinics in Erie County D000125Construction: BuildingActive | SUNY at Buffalo | Construction: BuildingConstruction | D000125 | Mar 25, 2026to Jan 15, 2028 | Mar 25, 2026 | Jan 15, 2028 | $570,000$73,955 spent | $73,955 | |
Orthodontic clinic renovations at Squire Hall in Erie county- electrical contractor D000080Construction: BuildingActive | SUNY at Buffalo | Construction: BuildingConstruction | D000080 | Dec 31, 2024to Dec 30, 2026 | Dec 31, 2024 | Dec 30, 2026 | $480,000$480,000 spent | $480,000 | |
PA filed contract SUNY Buffalo Ellicott Complex Phase 6 Red Jacket Quad including asbestos & HAZMAT D229780Contract not subject to state pre-audit | Dormitory Authority of the State of New York | Contract not subject to state pre-auditNot pre-audited | D229780 | Mar 27, 2025to Jul 21, 2026 | Mar 27, 2025 | Jul 21, 2026 | $2,130,000$0 spent | $0 | |
PA filed contract SUNY University at Buffalo ellicott electrical upgrades Phase 5 and asbestos D225242Contract not subject to state pre-audit | Dormitory Authority of the State of New York | Contract not subject to state pre-auditNot pre-audited | D225242 | Jan 18, 2024to Aug 1, 2025 | Jan 18, 2024 | Aug 1, 2025 | $1,811,000$0 spent | $0 | |
Replace emergency generators at SUNY Fredonia D006867Construction: Building | State University Construction Fund | Construction: BuildingConstruction | D006867 | Nov 29, 2023to Sep 14, 2026 | Nov 29, 2023 | Sep 14, 2026 | $2,443,050$2,443,050 spent | $2,443,050 | |
Main Stage House Lighting Upgrades Artpark State Park Niagara County D006183Construction: Building | Office of Parks Recreation & Historic Preservation | Construction: BuildingConstruction | D006183 | Nov 17, 2023to Apr 1, 2025 | Nov 17, 2023 | Apr 1, 2025 | $886,884$886,884 spent | $886,884 | |
Emergency generators replacement in Cooke, Hochstetter and Dorsheimer buildings at SUNY Buffalo D006813Construction: Miscellaneous | State University Construction Fund | Construction: MiscellaneousConstruction | D006813 | Apr 19, 2023to Jun 21, 2026 | Apr 19, 2023 | Jun 21, 2026 | $3,401,553$3,401,553 spent | $3,401,553 | |
PA Filed Contract SUNY Buffalo Ellicott Complex Fargo Quad Phase 4 electrical upgrades Erie County D221990Contract not subject to state pre-audit | Dormitory Authority of the State of New York | Contract not subject to state pre-auditNot pre-audited | D221990 | Feb 22, 2023to May 31, 2024 | Feb 22, 2023 | May 31, 2024 | $1,570,000$0 spent | $0 | |
Electrical work Kenan Castellani buildout phase 2 DeVeaux Woods SP Niagara County D005839Construction: Building | Office of Parks Recreation & Historic Preservation | Construction: BuildingConstruction | D005839 | Nov 19, 2021to Aug 16, 2022 | Nov 19, 2021 | Aug 16, 2022 | $420,117$420,117 spent | $420,117 | |
Provide facility wide CCTV/audio monitoring system and recording room Wende CF Erie County D45849EConstruction: Building | Office of General Services - Design & Construction | Construction: BuildingConstruction | D45849E | May 16, 2021to Jul 8, 2026 | May 16, 2021 | Jul 8, 2026 | $7,937,836$7,351,464 spent | $7,351,464 | |
Biomedical research building pharmacy renovation electric Buffalo Erie County D000005Construction: Building | SUNY at Buffalo | Construction: BuildingConstruction | D000005 | Mar 18, 2021to May 31, 2023 | Mar 18, 2021 | May 31, 2023 | $462,266$462,266 spent | $462,266 | |
Replacement of switchgear and panels at Upton Hall and Campbell student union building D200221Construction: Building | College at Buffalo | Construction: BuildingConstruction | D200221 | Jan 13, 2021to Mar 31, 2022 | Jan 13, 2021 | Mar 31, 2022 | $2,973,054$2,973,054 spent | $2,973,054 | |
Electrical construction for relocation of Buhite DiMino Center for Implant Dentistry D000002Construction: Miscellaneous | SUNY at Buffalo | Construction: MiscellaneousConstruction | D000002 | Dec 1, 2020to Oct 1, 2023 | Dec 1, 2020 | Oct 1, 2023 | $364,746$364,746 spent | $364,746 | |
Provide Classrooms & Office Space Bldg 34 Residential Rehab Unit Orleans CF Orleans County D46134EConstruction: Building | Office of General Services - Design & Construction | Construction: BuildingConstruction | D46134E | Sep 8, 2020to Mar 29, 2023 | Sep 8, 2020 | Mar 29, 2023 | $859,253$857,283 spent | $857,283 | |
Correct flood damage Building 51 Buffalo PC Erie County DEE393EConstruction: Building | Office of General Services - Design & Construction | Construction: BuildingConstruction | DEE393E | Jul 20, 2020to Feb 14, 2022 | Jul 20, 2020 | Feb 14, 2022 | $300,000$139,175 spent | $139,175 | |
Switchgear replacement in baco T180185Contract not subject to state pre-audit | College at Buffalo | Contract not subject to state pre-auditNot pre-audited | T180185 | Apr 3, 2019to Dec 31, 2019 | Apr 3, 2019 | Dec 31, 2019 | $990,236$493,236 spent | $493,236 | |
2017-091C library storage anne T500093Contract not subject to state pre-audit | SUNY at Buffalo | Contract not subject to state pre-auditNot pre-audited | T500093 | May 19, 2018to Dec 20, 2019 | May 19, 2018 | Dec 20, 2019 | $95,595$95,595 spent | $95,595 |
Falconwood roof replacement electrical work Beaver Island State Park Erie CountyOffice of Parks Recreation & Historic PreservationJul 23, 2026 – Apr 29, 2027Active$489,000
- Description
- Falconwood roof replacement electrical work Beaver Island State Park Erie County
- Contract number
- D006528
- Type
- Construction: BuildingConstruction
- Term
- Jul 23, 2026 → Apr 29, 20279 months
- Approved
- Jul 23, 2026
- Status
- Active
- Amount
- $489,000
- Spent to date
- $0 · 0% of the amount
Electrical work for lab renovation at Furnas Hall University at Buffalo in Erie CountySUNY at BuffaloMay 15, 2026 – Mar 30, 2028Active$780,000
- Description
- Electrical work for lab renovation at Furnas Hall University at Buffalo in Erie County
- Contract number
- D000129
- Type
- Construction: BuildingConstruction
- Agency
- SUNY at Buffalo
- Term
- May 15, 2026 → Mar 30, 20281.9 years
- Approved
- May 15, 2026
- Status
- Active
- Amount
- $780,000
- Spent to date
- $110,104 · 14% of the amount
Electrical work for lodge roofing replacement at Woodlawn Beach State Park in Erie CountyOffice of Parks Recreation & Historic PreservationApr 24, 2026 – May 29, 2027Active$490,000
- Description
- Electrical work for lodge roofing replacement at Woodlawn Beach State Park in Erie County
- Contract number
- D006529
- Type
- Construction: BuildingConstruction
- Term
- Apr 24, 2026 → May 29, 202713 months
- Approved
- Apr 24, 2026
- Status
- Active
- Amount
- $490,000
- Spent to date
- $0 · 0% of the amount
Electrical to renovate special care and oral facial pain clinics in Erie CountySUNY at BuffaloMar 25, 2026 – Jan 15, 2028Active$570,000
- Description
- Electrical to renovate special care and oral facial pain clinics in Erie County
- Contract number
- D000125
- Type
- Construction: BuildingConstruction
- Agency
- SUNY at Buffalo
- Term
- Mar 25, 2026 → Jan 15, 20281.8 years
- Approved
- Mar 25, 2026
- Status
- Active
- Amount
- $570,000
- Spent to date
- $73,955 · 13% of the amount
Orthodontic clinic renovations at Squire Hall in Erie county- electrical contractorSUNY at BuffaloDec 31, 2024 – Dec 30, 2026Active$480,000
- Description
- Orthodontic clinic renovations at Squire Hall in Erie county- electrical contractor
- Contract number
- D000080
- Type
- Construction: BuildingConstruction
- Agency
- SUNY at Buffalo
- Term
- Dec 31, 2024 → Dec 30, 20262 years
- Approved
- Dec 31, 2024
- Status
- Active
- Amount
- $480,000
- Spent to date
- $480,000 · 100% of the amount
PA filed contract SUNY Buffalo Ellicott Complex Phase 6 Red Jacket Quad including asbestos & HAZMATDormitory Authority of the State of New YorkMar 27, 2025 – Jul 21, 2026$2,130,000
- Description
- PA filed contract SUNY Buffalo Ellicott Complex Phase 6 Red Jacket Quad including asbestos & HAZMAT
- Contract number
- D229780
- Type
- Contract not subject to state pre-auditNot pre-audited
- Term
- Mar 27, 2025 → Jul 21, 202616 months
- Approved
- Apr 22, 2025
- Status
- Ended
- Amount
- $2,130,000
- Spent to date
- $0 · 0% of the amount
PA filed contract SUNY University at Buffalo ellicott electrical upgrades Phase 5 and asbestosDormitory Authority of the State of New YorkJan 18, 2024 – Aug 1, 2025$1,811,000
- Description
- PA filed contract SUNY University at Buffalo ellicott electrical upgrades Phase 5 and asbestos
- Contract number
- D225242
- Type
- Contract not subject to state pre-auditNot pre-audited
- Term
- Jan 18, 2024 → Aug 1, 20251.5 years
- Approved
- Mar 27, 2024
- Status
- Ended
- Amount
- $1,811,000
- Spent to date
- $0 · 0% of the amount
Replace emergency generators at SUNY FredoniaState University Construction FundNov 29, 2023 – Sep 14, 2026$2,443,050
- Description
- Replace emergency generators at SUNY Fredonia
- Contract number
- D006867
- Type
- Construction: BuildingConstruction
- Term
- Nov 29, 2023 → Sep 14, 20262.8 years
- Approved
- Nov 24, 2023
- Status
- Ended
- Amount
- $2,443,050
- Spent to date
- $2,443,050 · 100% of the amount
Main Stage House Lighting Upgrades Artpark State Park Niagara CountyOffice of Parks Recreation & Historic PreservationNov 17, 2023 – Apr 1, 2025$886,884
- Description
- Main Stage House Lighting Upgrades Artpark State Park Niagara County
- Contract number
- D006183
- Type
- Construction: BuildingConstruction
- Term
- Nov 17, 2023 → Apr 1, 202516 months
- Approved
- Nov 17, 2023
- Status
- Ended
- Amount
- $886,884
- Spent to date
- $886,884 · 100% of the amount
Emergency generators replacement in Cooke, Hochstetter and Dorsheimer buildings at SUNY BuffaloState University Construction FundApr 19, 2023 – Jun 21, 2026$3,401,553
- Description
- Emergency generators replacement in Cooke, Hochstetter and Dorsheimer buildings at SUNY Buffalo
- Contract number
- D006813
- Type
- Construction: MiscellaneousConstruction
- Term
- Apr 19, 2023 → Jun 21, 20263.2 years
- Approved
- Apr 17, 2023
- Status
- Ended
- Amount
- $3,401,553
- Spent to date
- $3,401,553 · 100% of the amount
PA Filed Contract SUNY Buffalo Ellicott Complex Fargo Quad Phase 4 electrical upgrades Erie CountyDormitory Authority of the State of New YorkFeb 22, 2023 – May 31, 2024$1,570,000
- Description
- PA Filed Contract SUNY Buffalo Ellicott Complex Fargo Quad Phase 4 electrical upgrades Erie County
- Contract number
- D221990
- Type
- Contract not subject to state pre-auditNot pre-audited
- Term
- Feb 22, 2023 → May 31, 202415 months
- Approved
- Mar 10, 2023
- Status
- Ended
- Amount
- $1,570,000
- Spent to date
- $0 · 0% of the amount
Electrical work Kenan Castellani buildout phase 2 DeVeaux Woods SP Niagara CountyOffice of Parks Recreation & Historic PreservationNov 19, 2021 – Aug 16, 2022$420,117
- Description
- Electrical work Kenan Castellani buildout phase 2 DeVeaux Woods SP Niagara County
- Contract number
- D005839
- Type
- Construction: BuildingConstruction
- Term
- Nov 19, 2021 → Aug 16, 20229 months
- Approved
- Nov 19, 2021
- Status
- Ended
- Amount
- $420,117
- Spent to date
- $420,117 · 100% of the amount
Provide facility wide CCTV/audio monitoring system and recording room Wende CF Erie CountyOffice of General Services - Design & ConstructionMay 16, 2021 – Jul 8, 2026$7,937,836
- Description
- Provide facility wide CCTV/audio monitoring system and recording room Wende CF Erie County
- Contract number
- D45849E
- Type
- Construction: BuildingConstruction
- Term
- May 16, 2021 → Jul 8, 20265.2 years
- Approved
- May 16, 2021
- Status
- Ended
- Amount
- $7,937,836
- Spent to date
- $7,351,464 · 93% of the amount
Biomedical research building pharmacy renovation electric Buffalo Erie CountySUNY at BuffaloMar 18, 2021 – May 31, 2023$462,266
- Description
- Biomedical research building pharmacy renovation electric Buffalo Erie County
- Contract number
- D000005
- Type
- Construction: BuildingConstruction
- Agency
- SUNY at Buffalo
- Term
- Mar 18, 2021 → May 31, 20232.2 years
- Approved
- Mar 18, 2021
- Status
- Ended
- Amount
- $462,266
- Spent to date
- $462,266 · 100% of the amount
Replacement of switchgear and panels at Upton Hall and Campbell student union buildingCollege at BuffaloJan 13, 2021 – Mar 31, 2022$2,973,054
- Description
- Replacement of switchgear and panels at Upton Hall and Campbell student union building
- Contract number
- D200221
- Type
- Construction: BuildingConstruction
- Agency
- College at Buffalo
- Term
- Jan 13, 2021 → Mar 31, 202215 months
- Approved
- Feb 8, 2021
- Status
- Ended
- Amount
- $2,973,054
- Spent to date
- $2,973,054 · 100% of the amount
Electrical construction for relocation of Buhite DiMino Center for Implant DentistrySUNY at BuffaloDec 1, 2020 – Oct 1, 2023$364,746
- Description
- Electrical construction for relocation of Buhite DiMino Center for Implant Dentistry
- Contract number
- D000002
- Type
- Construction: MiscellaneousConstruction
- Agency
- SUNY at Buffalo
- Term
- Dec 1, 2020 → Oct 1, 20232.8 years
- Approved
- Dec 14, 2020
- Status
- Ended
- Amount
- $364,746
- Spent to date
- $364,746 · 100% of the amount
Provide Classrooms & Office Space Bldg 34 Residential Rehab Unit Orleans CF Orleans CountyOffice of General Services - Design & ConstructionSep 8, 2020 – Mar 29, 2023$859,253
- Description
- Provide Classrooms & Office Space Bldg 34 Residential Rehab Unit Orleans CF Orleans County
- Contract number
- D46134E
- Type
- Construction: BuildingConstruction
- Term
- Sep 8, 2020 → Mar 29, 20232.6 years
- Approved
- Sep 8, 2020
- Status
- Ended
- Amount
- $859,253
- Spent to date
- $857,283 · 100% of the amount
Correct flood damage Building 51 Buffalo PC Erie CountyOffice of General Services - Design & ConstructionJul 20, 2020 – Feb 14, 2022$300,000
- Description
- Correct flood damage Building 51 Buffalo PC Erie County
- Contract number
- DEE393E
- Type
- Construction: BuildingConstruction
- Term
- Jul 20, 2020 → Feb 14, 20221.6 years
- Approved
- Sep 9, 2020
- Status
- Ended
- Amount
- $300,000
- Spent to date
- $139,175 · 46% of the amount
Switchgear replacement in bacoCollege at BuffaloApr 3, 2019 – Dec 31, 2019$990,236
- Description
- Switchgear replacement in baco
- Contract number
- T180185
- Type
- Contract not subject to state pre-auditNot pre-audited
- Agency
- College at Buffalo
- Term
- Apr 3, 2019 → Dec 31, 20199 months
- Approved
- Apr 4, 2019
- Status
- Ended
- Amount
- $990,236
- Spent to date
- $493,236 · 50% of the amount
2017-091C library storage anneSUNY at BuffaloMay 19, 2018 – Dec 20, 2019$95,595
- Description
- 2017-091C library storage anne
- Contract number
- T500093
- Type
- Contract not subject to state pre-auditNot pre-audited
- Agency
- SUNY at Buffalo
- Term
- May 19, 2018 → Dec 20, 20191.6 years
- Approved
- Jun 2, 2018
- Status
- Ended
- Amount
- $95,595
- Spent to date
- $95,595 · 100% of the amount
Contract-type mix
Share of contract value by type
- Construction26 contracts$28.7M
- Contract not subject to state pre-audit9 contracts$10.1M
Contracts over time
Contracts started per year
View as table
| Year | Contracts |
|---|---|
| 2007: 1 contracts, $1.9M | 1 |
| 2008: 0 contracts, $0.0 | 0 |
| 2009: 2 contracts, $308.9K | 2 |
| 2010: 1 contracts, $84.3K | 1 |
| 2011: 0 contracts, $0.0 | 0 |
| 2012: 4 contracts, $4.4M | 4 |
| 2013: 1 contracts, $829.0K | 1 |
| 2014: 2 contracts, $743.9K | 2 |
| 2015: 2 contracts, $309.3K | 2 |
| 2016: 2 contracts, $755.0K | 2 |
| 2017: 0 contracts, $0.0 | 0 |
| 2018: 1 contracts, $95.6K | 1 |
| 2019: 1 contracts, $990.2K | 1 |
| 2020: 3 contracts, $1.5M | 3 |
| 2021: 4 contracts, $11.8M | 4 |
| 2022: 0 contracts, $0.0 | 0 |
| 2023: 4 contracts, $8.3M | 4 |
| 2024: 2 contracts, $2.3M | 2 |
| 2025: 1 contracts, $2.1M | 1 |
| 2026: 4 contracts, $2.3M | 4 |
How the Contractor Score adds up
Extensive (A, 100/100): 5 active contracts, $39M in contracts.
- Contract volume+14.6measured
$39M in current contract value across 35 contracts, more than 93% of scored contractors.
- Recent activity+17.3measured
5 active contracts today; the most recent was approved in July 2026.
- Agency breadth+10.3measured
Contracts with 6 different state agencies and facilities.
- Experience+2.3measured
First contract started in July 2007 (19 years of contract history).
- Contract-type mix+5.0measured
3 contract types; the largest group is construction (74% of value). Goods and services contracts are 74% of the total.
- Spending vs. value0.0measured
On 27 completed contracts with spending recorded, spending is 95% of the contract value. Spending below the full value is common (work can finish under budget) and isn't treated as a problem.
- Federal award history0.0unknown
No federal award history found. Scored as neutral.
- Federal registration+5.2measured
Registered to do business with the federal government (registration active).
50 + contributions = 104.7, capped at 100Starts at 50. Bars: cool adds, warm subtracts.
Agencies served
Contract value with each agency or facility
- Office of General Services - Design & Construction8 contracts$12.6M
- State University Construction Fund4 contracts$9.1M
- Dormitory Authority of the State of New York3 contracts$5.5M
- Office of Parks Recreation & Historic Preservation11 contracts$4.6M
- College at Buffalo3 contracts$4.1M
- SUNY at Buffalo6 contracts$2.8M
Similar contractors
- A
Weydman Electric Inc
Tonawanda, NYConstruction & Renovation
Since 200810 agencies
- Contract value
- $34.4M
- Contracts
- 44
- Active
- 7
- A
John W Danforth Company
Tonawanda, NYConstruction & Renovation
Since 200722 agencies
- Contract value
- $97.0M
- Contracts
- 160
- Active
- 14
- A
Oconnell Electric Company Inc
Victor, NYConstruction & Renovation
Since 200052 agencies
- Contract value
- $251.8M
- Contracts
- 220
- Active
- 13
- A
Lechase Construction Services LLC
Rochester, NYConstruction & Renovation
Since 200522 agencies
- Contract value
- $698.8M
- Contracts
- 142
- Active
- 25
- A
Jameson Roofing Company Inc
Buffalo, NYConstruction & Renovation
Since 20095 agencies
- Contract value
- $28.0M
- Contracts
- 24
- Active
- 0
- A
MLP Plumbing & Mechanical Inc
Construction & Renovation
Since 20086 agencies
- Contract value
- $25.8M
- Contracts
- 55
- Active
- 6
- More construction & renovation contractors Ranked by contract value
Browse more
- Office of General Services - Design & Construction contractors
- State University Construction Fund contractors
- Dormitory Authority of the State of New York contractors
- Office of Parks Recreation & Historic Preservation contractors
- Construction & Renovation contractors
- Top contractors
- All contractors
Contract figures are public New York State contract records as of Nov 13, 2026: current contract amounts and spending to date as reported. Company details are shown when we can match this contractor to a registered business with confidence.
RFP Detector is an independent service and is not affiliated with any government agency. Scores are informational.