NY State contractorConstruction & Renovation

Natures Way Environmental Consultants and Contractor Inc

State contracts since 2009Updated Nov 13, 2026

Natures Way Environmental Consultants and Contractor Inc holds 26 contracts worth $66.9M with 6 New York State agencies, most with Office of General Services - Design & Construction; 2 active today. The first started in 2009.

Total contract value
$66.9M
Current contract amounts
Spent to date
$43.0M
64% of contract value
Active contracts
2
$8.3M in active value
Contracts on record
26
Since 2009
Agencies served
6
Most with Office of General Services - Design & Construction
Years active
17
First contract 2009

Contact & company

Business information and how to reach the company.

Company details for Natures Way Environmental Consultants and Contractor Inc haven't been confirmed yet. If this is your company, claim the profile to add your website, address and contacts.

Contracts

26 contracts with New York State agencies, active first. Open a row for the full record.

Contracts
DetailsContractTypeContract no.Term

Provide patrol road and secure perimeter modifications Collins Correctional Facility Erie County

D47324EConstruction: BuildingActive

Office of General Services - Design & ConstructionConstruction: BuildingConstructionD47324EMar 25, 2026to Jan 22, 2027Mar 25, 2026Jan 22, 2027$272,888$170,223 spent$170,223

Where & when fuel tank modification & environmental remediation Western Region various counties

D47676CConstruction: BuildingActive

Office of General Services - Design & ConstructionConstruction: BuildingConstructionD47676CJul 23, 2025to Oct 20, 2028Jul 23, 2025Oct 20, 2028$8,000,000$2,045,996 spent$2,045,996

Entrance monuments & paving at Letchworth State Park in Livingston and Wyoming Counties

D006425Construction: Building

Office of Parks Recreation & Historic PreservationConstruction: BuildingConstructionD006425Nov 18, 2025to Nov 18, 2026Nov 18, 2025Nov 18, 2026$1,586,290$1,117,906 spent$1,117,906

Provide pedestrian walkway & pavement restoration at Buffalo Armory in Erie County e trade

D47457EConstruction: Building

Office of General Services - Design & ConstructionConstruction: BuildingConstructionD47457EAug 7, 2024to Oct 26, 2025Aug 7, 2024Oct 26, 2025$177,724$176,774 spent$176,774

Parking lot & site improvements Woodlawn Beach State Park Erie County

D006260Construction: Building

Office of Parks Recreation & Historic PreservationConstruction: BuildingConstructionD006260Jul 2, 2024to Sep 30, 2025Jul 2, 2024Sep 30, 2025$2,021,912$2,021,912 spent$2,021,912

Decommission underground fuel station at Clinton Center in Niagara County

D230004Construction: Building

College at BuffaloConstruction: BuildingConstructionD230004Jun 26, 2024to Oct 24, 2024Jun 26, 2024Oct 24, 2024$177,224$177,224 spent$177,224

Construct main entry sign DeVeaux Woods State Park Niagara County

D006185Construction: Building

Office of Parks Recreation & Historic PreservationConstruction: BuildingConstructionD006185Dec 21, 2023to Jul 15, 2024Dec 21, 2023Jul 15, 2024$110,783$107,952 spent$107,952

Zoar Valley Valentine Flats access project phase 1 in Cattaraugus County

D012978Construction: Miscellaneous

Department of Environmental ConservationConstruction: MiscellaneousConstructionD012978Oct 27, 2023to Aug 30, 2024Oct 27, 2023Aug 30, 2024$790,692$782,106 spent$782,106

Wildlife Barrier Letchworth State Park Livingston Wyoming County

D006130Construction: Building

Office of Parks Recreation & Historic PreservationConstruction: BuildingConstructionD006130Jul 6, 2023to Jul 5, 2024Jul 6, 2023Jul 5, 2024$424,253$417,484 spent$417,484

Where & When for fuel tank modification and environmental remediation in the Western Region

D47050CConstruction: Building

Office of General Services - Design & ConstructionConstruction: BuildingConstructionD47050COct 26, 2022to Jun 12, 2025Oct 26, 2022Jun 12, 2025$11,866,865$5,446,736 spent$5,446,736

Wetland restoration Woodland Beach State Park Erie County

D005904Construction: Highway

Office of Parks Recreation & Historic PreservationConstruction: HighwayConstructionD005904Oct 18, 2022to Oct 18, 2023Oct 18, 2022Oct 18, 2023$1,655,240$1,392,505 spent$1,392,505

Resurfacing & enhancements Genesee Valley Greenway State Park Monroe county

D005797Construction: Building

Office of Parks Recreation & Historic PreservationConstruction: BuildingConstructionD005797Jun 8, 2021to Nov 30, 2022Jun 8, 2021Nov 30, 2022$1,805,482$1,650,887 spent$1,650,887

Remove contaminated soils Albion CF Orleans county

DEE550BConstruction: Building

Office of General Services - Design & ConstructionConstruction: BuildingConstructionDEE550BMar 17, 2021to Nov 12, 2021Mar 17, 2021Nov 12, 2021$300,000$19,259 spent$19,259

Replace Underground Storage Tanks Power House Building 19 Albion CF Orleans County

D45672HConstruction: Building

Office of General Services - Design & ConstructionConstruction: BuildingConstructionD45672HSep 25, 2020to Jan 8, 2022Sep 25, 2020Jan 8, 2022$1,875,653$1,875,570 spent$1,875,570

Replace Underground Storage Tanks Power House Building 19 Albion CF Orleans County

D45672CConstruction: Building

Office of General Services - Design & ConstructionConstruction: BuildingConstructionD45672CSep 25, 2020to Dec 4, 2021Sep 25, 2020Dec 4, 2021$1,023,811$1,023,619 spent$1,023,619

2020-21 Osh t & e

T20040GGContract not subject to state pre-audit

Department of LaborContract not subject to state pre-auditNot pre-auditedT20040GGAug 1, 2020to Jul 31, 2021Aug 1, 2020Jul 31, 2021$10,164$600 spent$600

2019-20 Osh t & e

T19044GGContract not subject to state pre-audit

Department of LaborContract not subject to state pre-auditNot pre-auditedT19044GGAug 1, 2019to Jul 31, 2020Aug 1, 2019Jul 31, 2020$23,664$7,625 spent$7,625

Ralph C Wilson Jr Gateway Buffalo Harbor State Park Erie County

D005508Construction: Building

Office of Parks Recreation & Historic PreservationConstruction: BuildingConstructionD005508Mar 13, 2019to Dec 8, 2019Mar 13, 2019Dec 8, 2019$505,353$501,353 spent$501,353

Where & When Fuel Tank Modification & Environmental Remediation Various Facilities Western Region

D45534CConstruction: Standby contracts

Office of General Services - Design & ConstructionConstruction: Standby contractsConstructionD45534CMay 22, 2018to Aug 21, 2023May 22, 2018Aug 21, 2023$6,000,000$4,335,820 spent$4,335,820

Standby Investigation and Remediation - Regions 8, and 9

C100612Consultant: Environmental related services

Department of Environmental Conservation - Oil SpillConsultant: Environmental related servicesConsultantC100612Apr 1, 2016to Mar 31, 2023Apr 1, 2016Mar 31, 2023$12,000,000$8,213,451 spent$8,213,451
Provide patrol road and secure perimeter modifications Collins Correctional Facility Erie CountyOffice of General Services - Design & ConstructionMar 25, 2026 – Jan 22, 2027Active$272,888
Description
Provide patrol road and secure perimeter modifications Collins Correctional Facility Erie County
Contract number
D47324E
Type
Construction: BuildingConstruction
Term
Mar 25, 2026 → Jan 22, 202710 months
Approved
Mar 25, 2026
Status
Active
Amount
$272,888
Spent to date
$170,223 · 62% of the amount
Where & when fuel tank modification & environmental remediation Western Region various countiesOffice of General Services - Design & ConstructionJul 23, 2025 – Oct 20, 2028Active$8,000,000
Description
Where & when fuel tank modification & environmental remediation Western Region various counties
Contract number
D47676C
Type
Construction: BuildingConstruction
Term
Jul 23, 2025 → Oct 20, 20283.3 years
Approved
Jul 23, 2025
Status
Active
Amount
$8,000,000
Spent to date
$2,045,996 · 26% of the amount
Entrance monuments & paving at Letchworth State Park in Livingston and Wyoming CountiesOffice of Parks Recreation & Historic PreservationNov 18, 2025 – Nov 18, 2026$1,586,290
Description
Entrance monuments & paving at Letchworth State Park in Livingston and Wyoming Counties
Contract number
D006425
Type
Construction: BuildingConstruction
Term
Nov 18, 2025 → Nov 18, 202612 months
Approved
Nov 18, 2025
Status
Ended
Amount
$1,586,290
Spent to date
$1,117,906 · 70% of the amount
Provide pedestrian walkway & pavement restoration at Buffalo Armory in Erie County e tradeOffice of General Services - Design & ConstructionAug 7, 2024 – Oct 26, 2025$177,724
Description
Provide pedestrian walkway & pavement restoration at Buffalo Armory in Erie County e trade
Contract number
D47457E
Type
Construction: BuildingConstruction
Term
Aug 7, 2024 → Oct 26, 202515 months
Approved
Aug 7, 2024
Status
Ended
Amount
$177,724
Spent to date
$176,774 · 99% of the amount
Parking lot & site improvements Woodlawn Beach State Park Erie CountyOffice of Parks Recreation & Historic PreservationJul 2, 2024 – Sep 30, 2025$2,021,912
Description
Parking lot & site improvements Woodlawn Beach State Park Erie County
Contract number
D006260
Type
Construction: BuildingConstruction
Term
Jul 2, 2024 → Sep 30, 202515 months
Approved
Jul 2, 2024
Status
Ended
Amount
$2,021,912
Spent to date
$2,021,912 · 100% of the amount
Decommission underground fuel station at Clinton Center in Niagara CountyCollege at BuffaloJun 26, 2024 – Oct 24, 2024$177,224
Description
Decommission underground fuel station at Clinton Center in Niagara County
Contract number
D230004
Type
Construction: BuildingConstruction
Term
Jun 26, 2024 → Oct 24, 20244 months
Approved
Jun 26, 2024
Status
Ended
Amount
$177,224
Spent to date
$177,224 · 100% of the amount
Construct main entry sign DeVeaux Woods State Park Niagara CountyOffice of Parks Recreation & Historic PreservationDec 21, 2023 – Jul 15, 2024$110,783
Description
Construct main entry sign DeVeaux Woods State Park Niagara County
Contract number
D006185
Type
Construction: BuildingConstruction
Term
Dec 21, 2023 → Jul 15, 20247 months
Approved
Dec 21, 2023
Status
Ended
Amount
$110,783
Spent to date
$107,952 · 97% of the amount
Zoar Valley Valentine Flats access project phase 1 in Cattaraugus CountyDepartment of Environmental ConservationOct 27, 2023 – Aug 30, 2024$790,692
Description
Zoar Valley Valentine Flats access project phase 1 in Cattaraugus County
Contract number
D012978
Type
Construction: MiscellaneousConstruction
Term
Oct 27, 2023 → Aug 30, 202410 months
Approved
Oct 27, 2023
Status
Ended
Amount
$790,692
Spent to date
$782,106 · 99% of the amount
Wildlife Barrier Letchworth State Park Livingston Wyoming CountyOffice of Parks Recreation & Historic PreservationJul 6, 2023 – Jul 5, 2024$424,253
Description
Wildlife Barrier Letchworth State Park Livingston Wyoming County
Contract number
D006130
Type
Construction: BuildingConstruction
Term
Jul 6, 2023 → Jul 5, 202412 months
Approved
Jul 6, 2023
Status
Ended
Amount
$424,253
Spent to date
$417,484 · 98% of the amount
Where & When for fuel tank modification and environmental remediation in the Western RegionOffice of General Services - Design & ConstructionOct 26, 2022 – Jun 12, 2025$11,866,865
Description
Where & When for fuel tank modification and environmental remediation in the Western Region
Contract number
D47050C
Type
Construction: BuildingConstruction
Term
Oct 26, 2022 → Jun 12, 20252.7 years
Approved
Oct 26, 2022
Status
Ended
Amount
$11,866,865
Spent to date
$5,446,736 · 46% of the amount
Wetland restoration Woodland Beach State Park Erie CountyOffice of Parks Recreation & Historic PreservationOct 18, 2022 – Oct 18, 2023$1,655,240
Description
Wetland restoration Woodland Beach State Park Erie County
Contract number
D005904
Type
Construction: HighwayConstruction
Term
Oct 18, 2022 → Oct 18, 202312 months
Approved
Oct 18, 2022
Status
Ended
Amount
$1,655,240
Spent to date
$1,392,505 · 84% of the amount
Resurfacing & enhancements Genesee Valley Greenway State Park Monroe countyOffice of Parks Recreation & Historic PreservationJun 8, 2021 – Nov 30, 2022$1,805,482
Description
Resurfacing & enhancements Genesee Valley Greenway State Park Monroe county
Contract number
D005797
Type
Construction: BuildingConstruction
Term
Jun 8, 2021 → Nov 30, 20221.5 years
Approved
Jun 8, 2021
Status
Ended
Amount
$1,805,482
Spent to date
$1,650,887 · 91% of the amount
Remove contaminated soils Albion CF Orleans countyOffice of General Services - Design & ConstructionMar 17, 2021 – Nov 12, 2021$300,000
Description
Remove contaminated soils Albion CF Orleans county
Contract number
DEE550B
Type
Construction: BuildingConstruction
Term
Mar 17, 2021 → Nov 12, 20218 months
Approved
Apr 23, 2021
Status
Ended
Amount
$300,000
Spent to date
$19,259 · 6% of the amount
Replace Underground Storage Tanks Power House Building 19 Albion CF Orleans CountyOffice of General Services - Design & ConstructionSep 25, 2020 – Jan 8, 2022$1,875,653
Description
Replace Underground Storage Tanks Power House Building 19 Albion CF Orleans County
Contract number
D45672H
Type
Construction: BuildingConstruction
Term
Sep 25, 2020 → Jan 8, 202215 months
Approved
Sep 25, 2020
Status
Ended
Amount
$1,875,653
Spent to date
$1,875,570 · 100% of the amount
Replace Underground Storage Tanks Power House Building 19 Albion CF Orleans CountyOffice of General Services - Design & ConstructionSep 25, 2020 – Dec 4, 2021$1,023,811
Description
Replace Underground Storage Tanks Power House Building 19 Albion CF Orleans County
Contract number
D45672C
Type
Construction: BuildingConstruction
Term
Sep 25, 2020 → Dec 4, 202114 months
Approved
Sep 25, 2020
Status
Ended
Amount
$1,023,811
Spent to date
$1,023,619 · 100% of the amount
2020-21 Osh t & eDepartment of LaborAug 1, 2020 – Jul 31, 2021$10,164
Description
2020-21 Osh t & e
Contract number
T20040GG
Type
Contract not subject to state pre-auditNot pre-audited
Term
Aug 1, 2020 → Jul 31, 202112 months
Approved
Jun 2, 2021
Status
Ended
Amount
$10,164
Spent to date
$600 · 6% of the amount
2019-20 Osh t & eDepartment of LaborAug 1, 2019 – Jul 31, 2020$23,664
Description
2019-20 Osh t & e
Contract number
T19044GG
Type
Contract not subject to state pre-auditNot pre-audited
Term
Aug 1, 2019 → Jul 31, 202012 months
Approved
Jul 18, 2019
Status
Ended
Amount
$23,664
Spent to date
$7,625 · 32% of the amount
Ralph C Wilson Jr Gateway Buffalo Harbor State Park Erie CountyOffice of Parks Recreation & Historic PreservationMar 13, 2019 – Dec 8, 2019$505,353
Description
Ralph C Wilson Jr Gateway Buffalo Harbor State Park Erie County
Contract number
D005508
Type
Construction: BuildingConstruction
Term
Mar 13, 2019 → Dec 8, 20199 months
Approved
Mar 13, 2019
Status
Ended
Amount
$505,353
Spent to date
$501,353 · 99% of the amount
Where & When Fuel Tank Modification & Environmental Remediation Various Facilities Western RegionOffice of General Services - Design & ConstructionMay 22, 2018 – Aug 21, 2023$6,000,000
Description
Where & When Fuel Tank Modification & Environmental Remediation Various Facilities Western Region
Contract number
D45534C
Type
Construction: Standby contractsConstruction
Term
May 22, 2018 → Aug 21, 20235.3 years
Approved
May 22, 2018
Status
Ended
Amount
$6,000,000
Spent to date
$4,335,820 · 72% of the amount
Standby Investigation and Remediation - Regions 8, and 9Department of Environmental Conservation - Oil SpillApr 1, 2016 – Mar 31, 2023$12,000,000
Description
Standby Investigation and Remediation - Regions 8, and 9
Contract number
C100612
Type
Consultant: Environmental related servicesConsultant
Term
Apr 1, 2016 → Mar 31, 20237 years
Approved
Oct 18, 2016
Status
Ended
Amount
$12,000,000
Spent to date
$8,213,451 · 68% of the amount
1–20 of 26Page 1 of 2

Contract-type mix

Share of contract value by type

Contracts over time

Contracts started per year

View as table
YearContracts
2009: 1 contracts, $5.0M1
2010: 0 contracts, $0.00
2011: 1 contracts, $200.0K1
2012: 2 contracts, $4.3M2
2013: 0 contracts, $0.00
2014: 1 contracts, $6.0M1
2015: 1 contracts, $744.4K1
2016: 1 contracts, $12.0M1
2017: 0 contracts, $0.00
2018: 1 contracts, $6.0M1
2019: 2 contracts, $529.0K2
2020: 3 contracts, $2.9M3
2021: 2 contracts, $2.1M2
2022: 2 contracts, $13.5M2
2023: 3 contracts, $1.3M3
2024: 3 contracts, $2.4M3
2025: 2 contracts, $9.6M2
2026: 1 contracts, $272.9K1

How the Contractor Score adds up

Extensive (A, 100/100): $67M in contracts, 2 active contracts.

  • Contract volume+16.4measured

    $67M in current contract value across 26 contracts, more than 95% of scored contractors.

  • Recent activity+14.0measured

    2 active contracts today; the most recent was approved in March 2026.

  • Agency breadth+10.3measured

    Contracts with 6 different state agencies and facilities.

  • Experience+1.8measured

    First contract started in February 2009 (17 years of contract history).

  • Contract-type mix+7.9measured

    6 contract types; the largest group is construction (75% of value). Goods and services contracts are 100% of the total.

  • Spending vs. value−0.7measured

    On 24 completed contracts with spending recorded, spending is 70% of the contract value. Spending below the full value is common (work can finish under budget) and isn't treated as a problem.

  • Federal award history0.0unknown

    No federal award history found. Scored as neutral.

  • Federal registration0.0unknown

    No federal contractor registration found. Scored as neutral.

50 + contributions = 100 (A, Extensive)Starts at 50. Bars: cool adds, warm subtracts.

Agencies served

Contract value with each agency or facility

Browse more

Contract figures are public New York State contract records as of Nov 13, 2026: current contract amounts and spending to date as reported. Company details are shown when we can match this contractor to a registered business with confidence.