Willett Builders Inc
AState contracts since 2015Updated Nov 13, 2026
Willett Builders Inc holds 19 contracts worth $7.6M with 6 New York State agencies, most with Office of General Services - Design & Construction; 3 active today. The first started in 2015.
- Total contract value
- $7.6M
- Current contract amounts
- Spent to date
- $4.8M
- 63% of contract value
- Active contracts
- 3
- $1.9M in active value
- Contracts on record
- 19
- Since 2015
- Agencies served
- 6
- Most with Office of General Services - Design & Construction
- Years active
- 11
- First contract 2015
Contact & company
Business information and how to reach the company.
Contracts
19 contracts with New York State agencies, active first. Open a row for the full record.
| Details | Contract | Type | Contract no. | Term | |||||
|---|---|---|---|---|---|---|---|---|---|
Plumbing renovate third floor for Microbiome Facility at the University at Buffalo in Erie County D000142Construction: BuildingActive | SUNY at Buffalo | Construction: BuildingConstruction | D000142 | Aug 24, 2026to Jan 3, 2029 | Aug 24, 2026 | Jan 3, 2029 | $527,702$26,125 spent | $26,125 | |
Baird Hall classroom renovation in Erie County for plumbing and fire protection D000089Construction: BuildingActive | SUNY at Buffalo | Construction: BuildingConstruction | D000089 | Jun 24, 2025to Aug 14, 2027 | Jun 24, 2025 | Aug 14, 2027 | $344,432$316,007 spent | $316,007 | |
Job Order Contract for plumbing work in Area 8 D47738PConstruction: BuildingActive | Office of General Services - Design & Construction | Construction: BuildingConstruction | D47738P | Jun 23, 2025to Jun 23, 2027 | Jun 23, 2025 | Jun 23, 2027 | $1,000,000$0 spent | $0 | |
PA Filed Contract SUNY Buffalo Spaulding & Red Jacket water heater replacement D228601Contract not subject to state pre-audit | Dormitory Authority of the State of New York | Contract not subject to state pre-auditNot pre-audited | D228601 | Jan 7, 2025to Aug 1, 2025 | Jan 7, 2025 | Aug 1, 2025 | $1,220,000$0 spent | $0 | |
Repair steam condensate for the sports arena in Erie County D230005Construction: Building | College at Buffalo | Construction: BuildingConstruction | D230005 | May 30, 2024to Nov 8, 2024 | May 30, 2024 | Nov 8, 2024 | $907,758$907,758 spent | $907,758 | |
Main stage domestic water heater replacement Artpark State Park Town of Lewiston Niagara County D006155Construction: Building | Office of Parks Recreation & Historic Preservation | Construction: BuildingConstruction | D006155 | Oct 6, 2023to Apr 3, 2024 | Oct 6, 2023 | Apr 3, 2024 | $307,000$292,348 spent | $292,348 | |
Diehl comfort station Allegany State Park HVAC Cattaraugus County D005952Construction: Building | Office of Parks Recreation & Historic Preservation | Construction: BuildingConstruction | D005952 | Oct 18, 2022to Oct 18, 2023 | Oct 18, 2022 | Oct 18, 2023 | $165,091$161,748 spent | $161,748 | |
Natural sciences center toilet room renovation Erie County D000023Construction: Building | SUNY at Buffalo | Construction: BuildingConstruction | D000023 | Mar 4, 2022to Aug 12, 2023 | Mar 4, 2022 | Aug 12, 2023 | $603,848$603,848 spent | $603,848 | |
Provide Classrooms & Office Space Bldg 130 Residential Rehab Unit Collins CF Erie County D46129HConstruction: Building | Office of General Services - Design & Construction | Construction: BuildingConstruction | D46129H | Aug 14, 2020to Nov 30, 2022 | Aug 14, 2020 | Nov 30, 2022 | $1,137,918$1,132,067 spent | $1,132,067 | |
Replace Roof NYS Police Batavia Troop A Headquarters Genesee County D45600HConstruction: Building | Office of General Services - Design & Construction | Construction: BuildingConstruction | D45600H | Jun 12, 2019to Sep 13, 2020 | Jun 12, 2019 | Sep 13, 2020 | $603,004$600,753 spent | $600,753 | |
Project 2017-091d - library ST T500106Contract not subject to state pre-audit | SUNY at Buffalo | Contract not subject to state pre-auditNot pre-audited | T500106 | Mar 15, 2019to Mar 31, 2020 | Mar 15, 2019 | Mar 31, 2020 | $99,900$66,405 spent | $66,405 | |
Project i10430 - centre point T000335Contract not subject to state pre-audit | College at Fredonia | Contract not subject to state pre-auditNot pre-audited | T000335 | Mar 15, 2019to Aug 26, 2019 | Mar 15, 2019 | Aug 26, 2019 | $17,000$17,000 spent | $17,000 | |
Repurposing South Pool Complex Letchworth State Park Wyoming County P D005497Construction: Building | Office of Parks Recreation & Historic Preservation | Construction: BuildingConstruction | D005497 | Mar 12, 2019to Jul 4, 2020 | Mar 12, 2019 | Jul 4, 2020 | $235,700$233,278 spent | $233,278 | |
South pool complex mechanical T005496Contract not subject to state pre-audit | Office of Parks Recreation & Historic Preservation | Contract not subject to state pre-auditNot pre-audited | T005496 | Mar 12, 2019to Jul 4, 2020 | Mar 12, 2019 | Jul 4, 2020 | $22,675$22,000 spent | $22,000 | |
Project 2017-0918 library stor T500092Contract not subject to state pre-audit | SUNY at Buffalo | Contract not subject to state pre-auditNot pre-audited | T500092 | Jun 4, 2018to Mar 31, 2020 | Jun 4, 2018 | Mar 31, 2020 | $241,189$241,189 spent | $241,189 | |
Project d059ha - kirkland comp T000293Contract not subject to state pre-audit | College at Fredonia | Contract not subject to state pre-auditNot pre-audited | T000293 | Nov 16, 2016to Jan 9, 2017 | Nov 16, 2016 | Jan 9, 2017 | $27,886$27,886 spent | $27,886 | |
Replacement of Beach Comfort Station Darien Lakes SP Genesee County Plumbing D004830Construction: Building | Office of Parks Recreation & Historic Preservation | Construction: BuildingConstruction | D004830 | Jun 27, 2016to May 31, 2017 | Jun 27, 2016 | May 31, 2017 | $75,000$73,598 spent | $73,598 | |
Project m05479 - university co T000275Contract not subject to state pre-audit | College at Fredonia | Contract not subject to state pre-auditNot pre-audited | T000275 | Nov 4, 2015to Feb 20, 2016 | Nov 4, 2015 | Feb 20, 2016 | $24,570$24,570 spent | $24,570 | |
Project m05443 maytum hall mec T000256Contract not subject to state pre-audit | College at Fredonia | Contract not subject to state pre-auditNot pre-audited | T000256 | Feb 12, 2015to Jun 5, 2015 | Feb 12, 2015 | Jun 5, 2015 | $29,990$29,990 spent | $29,990 |
Plumbing renovate third floor for Microbiome Facility at the University at Buffalo in Erie CountySUNY at BuffaloAug 24, 2026 – Jan 3, 2029Active$527,702
- Description
- Plumbing renovate third floor for Microbiome Facility at the University at Buffalo in Erie County
- Contract number
- D000142
- Type
- Construction: BuildingConstruction
- Agency
- SUNY at Buffalo
- Term
- Aug 24, 2026 → Jan 3, 20292.3 years
- Approved
- Aug 24, 2026
- Status
- Active
- Amount
- $527,702
- Spent to date
- $26,125 · 5% of the amount
Baird Hall classroom renovation in Erie County for plumbing and fire protectionSUNY at BuffaloJun 24, 2025 – Aug 14, 2027Active$344,432
- Description
- Baird Hall classroom renovation in Erie County for plumbing and fire protection
- Contract number
- D000089
- Type
- Construction: BuildingConstruction
- Agency
- SUNY at Buffalo
- Term
- Jun 24, 2025 → Aug 14, 20272.2 years
- Approved
- Jun 24, 2025
- Status
- Active
- Amount
- $344,432
- Spent to date
- $316,007 · 92% of the amount
Job Order Contract for plumbing work in Area 8Office of General Services - Design & ConstructionJun 23, 2025 – Jun 23, 2027Active$1,000,000
- Description
- Job Order Contract for plumbing work in Area 8
- Contract number
- D47738P
- Type
- Construction: BuildingConstruction
- Term
- Jun 23, 2025 → Jun 23, 20272 years
- Approved
- Jun 23, 2025
- Status
- Active
- Amount
- $1,000,000
- Spent to date
- $0 · 0% of the amount
PA Filed Contract SUNY Buffalo Spaulding & Red Jacket water heater replacementDormitory Authority of the State of New YorkJan 7, 2025 – Aug 1, 2025$1,220,000
- Description
- PA Filed Contract SUNY Buffalo Spaulding & Red Jacket water heater replacement
- Contract number
- D228601
- Type
- Contract not subject to state pre-auditNot pre-audited
- Term
- Jan 7, 2025 → Aug 1, 20257 months
- Approved
- Jan 21, 2025
- Status
- Ended
- Amount
- $1,220,000
- Spent to date
- $0 · 0% of the amount
Repair steam condensate for the sports arena in Erie CountyCollege at BuffaloMay 30, 2024 – Nov 8, 2024$907,758
- Description
- Repair steam condensate for the sports arena in Erie County
- Contract number
- D230005
- Type
- Construction: BuildingConstruction
- Agency
- College at Buffalo
- Term
- May 30, 2024 → Nov 8, 20245 months
- Approved
- May 30, 2024
- Status
- Ended
- Amount
- $907,758
- Spent to date
- $907,758 · 100% of the amount
Main stage domestic water heater replacement Artpark State Park Town of Lewiston Niagara CountyOffice of Parks Recreation & Historic PreservationOct 6, 2023 – Apr 3, 2024$307,000
- Description
- Main stage domestic water heater replacement Artpark State Park Town of Lewiston Niagara County
- Contract number
- D006155
- Type
- Construction: BuildingConstruction
- Term
- Oct 6, 2023 → Apr 3, 20246 months
- Approved
- Oct 6, 2023
- Status
- Ended
- Amount
- $307,000
- Spent to date
- $292,348 · 95% of the amount
Diehl comfort station Allegany State Park HVAC Cattaraugus CountyOffice of Parks Recreation & Historic PreservationOct 18, 2022 – Oct 18, 2023$165,091
- Description
- Diehl comfort station Allegany State Park HVAC Cattaraugus County
- Contract number
- D005952
- Type
- Construction: BuildingConstruction
- Term
- Oct 18, 2022 → Oct 18, 202312 months
- Approved
- Oct 18, 2022
- Status
- Ended
- Amount
- $165,091
- Spent to date
- $161,748 · 98% of the amount
Natural sciences center toilet room renovation Erie CountySUNY at BuffaloMar 4, 2022 – Aug 12, 2023$603,848
- Description
- Natural sciences center toilet room renovation Erie County
- Contract number
- D000023
- Type
- Construction: BuildingConstruction
- Agency
- SUNY at Buffalo
- Term
- Mar 4, 2022 → Aug 12, 202317 months
- Approved
- Mar 4, 2022
- Status
- Ended
- Amount
- $603,848
- Spent to date
- $603,848 · 100% of the amount
Provide Classrooms & Office Space Bldg 130 Residential Rehab Unit Collins CF Erie CountyOffice of General Services - Design & ConstructionAug 14, 2020 – Nov 30, 2022$1,137,918
- Description
- Provide Classrooms & Office Space Bldg 130 Residential Rehab Unit Collins CF Erie County
- Contract number
- D46129H
- Type
- Construction: BuildingConstruction
- Term
- Aug 14, 2020 → Nov 30, 20222.3 years
- Approved
- Aug 14, 2020
- Status
- Ended
- Amount
- $1,137,918
- Spent to date
- $1,132,067 · 99% of the amount
Replace Roof NYS Police Batavia Troop A Headquarters Genesee CountyOffice of General Services - Design & ConstructionJun 12, 2019 – Sep 13, 2020$603,004
- Description
- Replace Roof NYS Police Batavia Troop A Headquarters Genesee County
- Contract number
- D45600H
- Type
- Construction: BuildingConstruction
- Term
- Jun 12, 2019 → Sep 13, 202015 months
- Approved
- Jun 12, 2019
- Status
- Ended
- Amount
- $603,004
- Spent to date
- $600,753 · 100% of the amount
Project 2017-091d - library STSUNY at BuffaloMar 15, 2019 – Mar 31, 2020$99,900
- Description
- Project 2017-091d - library ST
- Contract number
- T500106
- Type
- Contract not subject to state pre-auditNot pre-audited
- Agency
- SUNY at Buffalo
- Term
- Mar 15, 2019 → Mar 31, 202013 months
- Approved
- Feb 19, 2019
- Status
- Ended
- Amount
- $99,900
- Spent to date
- $66,405 · 66% of the amount
Project i10430 - centre pointCollege at FredoniaMar 15, 2019 – Aug 26, 2019$17,000
- Description
- Project i10430 - centre point
- Contract number
- T000335
- Type
- Contract not subject to state pre-auditNot pre-audited
- Agency
- College at Fredonia
- Term
- Mar 15, 2019 → Aug 26, 20195 months
- Approved
- Mar 20, 2019
- Status
- Ended
- Amount
- $17,000
- Spent to date
- $17,000 · 100% of the amount
Repurposing South Pool Complex Letchworth State Park Wyoming County POffice of Parks Recreation & Historic PreservationMar 12, 2019 – Jul 4, 2020$235,700
- Description
- Repurposing South Pool Complex Letchworth State Park Wyoming County P
- Contract number
- D005497
- Type
- Construction: BuildingConstruction
- Term
- Mar 12, 2019 → Jul 4, 202016 months
- Approved
- Mar 12, 2019
- Status
- Ended
- Amount
- $235,700
- Spent to date
- $233,278 · 99% of the amount
South pool complex mechanicalOffice of Parks Recreation & Historic PreservationMar 12, 2019 – Jul 4, 2020$22,675
- Description
- South pool complex mechanical
- Contract number
- T005496
- Type
- Contract not subject to state pre-auditNot pre-audited
- Term
- Mar 12, 2019 → Jul 4, 202016 months
- Approved
- Feb 25, 2019
- Status
- Ended
- Amount
- $22,675
- Spent to date
- $22,000 · 97% of the amount
Project 2017-0918 library storSUNY at BuffaloJun 4, 2018 – Mar 31, 2020$241,189
- Description
- Project 2017-0918 library stor
- Contract number
- T500092
- Type
- Contract not subject to state pre-auditNot pre-audited
- Agency
- SUNY at Buffalo
- Term
- Jun 4, 2018 → Mar 31, 20201.8 years
- Approved
- Jun 15, 2018
- Status
- Ended
- Amount
- $241,189
- Spent to date
- $241,189 · 100% of the amount
Project d059ha - kirkland compCollege at FredoniaNov 16, 2016 – Jan 9, 2017$27,886
- Description
- Project d059ha - kirkland comp
- Contract number
- T000293
- Type
- Contract not subject to state pre-auditNot pre-audited
- Agency
- College at Fredonia
- Term
- Nov 16, 2016 → Jan 9, 20172 months
- Approved
- Nov 22, 2016
- Status
- Ended
- Amount
- $27,886
- Spent to date
- $27,886 · 100% of the amount
Replacement of Beach Comfort Station Darien Lakes SP Genesee County PlumbingOffice of Parks Recreation & Historic PreservationJun 27, 2016 – May 31, 2017$75,000
- Description
- Replacement of Beach Comfort Station Darien Lakes SP Genesee County Plumbing
- Contract number
- D004830
- Type
- Construction: BuildingConstruction
- Term
- Jun 27, 2016 → May 31, 201711 months
- Approved
- Jun 27, 2016
- Status
- Ended
- Amount
- $75,000
- Spent to date
- $73,598 · 98% of the amount
Project m05479 - university coCollege at FredoniaNov 4, 2015 – Feb 20, 2016$24,570
- Description
- Project m05479 - university co
- Contract number
- T000275
- Type
- Contract not subject to state pre-auditNot pre-audited
- Agency
- College at Fredonia
- Term
- Nov 4, 2015 → Feb 20, 20164 months
- Approved
- Dec 18, 2015
- Status
- Ended
- Amount
- $24,570
- Spent to date
- $24,570 · 100% of the amount
Project m05443 maytum hall mecCollege at FredoniaFeb 12, 2015 – Jun 5, 2015$29,990
- Description
- Project m05443 maytum hall mec
- Contract number
- T000256
- Type
- Contract not subject to state pre-auditNot pre-audited
- Agency
- College at Fredonia
- Term
- Feb 12, 2015 → Jun 5, 20154 months
- Approved
- Mar 14, 2015
- Status
- Ended
- Amount
- $29,990
- Spent to date
- $29,990 · 100% of the amount
Contract-type mix
Share of contract value by type
- Construction: Building11 contracts$5.9M
- Contract not subject to state pre-audit8 contracts$1.7M
Contracts over time
Contracts started per year
View as table
| Year | Contracts |
|---|---|
| 2015: 2 contracts, $54.6K | 2 |
| 2016: 2 contracts, $102.9K | 2 |
| 2017: 0 contracts, $0.0 | 0 |
| 2018: 1 contracts, $241.2K | 1 |
| 2019: 5 contracts, $978.3K | 5 |
| 2020: 1 contracts, $1.1M | 1 |
| 2021: 0 contracts, $0.0 | 0 |
| 2022: 2 contracts, $768.9K | 2 |
| 2023: 1 contracts, $307.0K | 1 |
| 2024: 1 contracts, $907.8K | 1 |
| 2025: 3 contracts, $2.6M | 3 |
| 2026: 1 contracts, $527.7K | 1 |
How the Contractor Score adds up
Extensive (A, 89/100): 3 active contracts, works with 6 agencies.
- Contract volume+9.4measured
$7.6M in current contract value across 19 contracts, more than 83% of scored contractors.
- Recent activity+15.9measured
3 active contracts today; the most recent was approved in August 2026.
- Agency breadth+10.3measured
Contracts with 6 different state agencies and facilities.
- Experience−0.7measured
First contract started in February 2015 (11 years of contract history).
- Contract-type mix+4.0measured
2 contract types; the largest group is construction (78% of value). Goods and services contracts are 78% of the total.
- Spending vs. value+0.1measured
On 15 completed contracts with spending recorded, spending is 99% of the contract value. Spending below the full value is common (work can finish under budget) and isn't treated as a problem.
- Federal award history0.0unknown
No federal award history found. Scored as neutral.
- Federal registration0.0unknown
No federal contractor registration found. Scored as neutral.
50 + contributions = 89 (A, Extensive)Starts at 50. Bars: cool adds, warm subtracts.
Agencies served
Contract value with each agency or facility
Similar contractors
- A
John W Danforth Company
Tonawanda, NYConstruction & Renovation
Since 200722 agencies
- Contract value
- $97.0M
- Contracts
- 160
- Active
- 14
- A
Oconnell Electric Company Inc
Victor, NYConstruction & Renovation
Since 200052 agencies
- Contract value
- $251.8M
- Contracts
- 220
- Active
- 13
- A
Mollenberg-Betz Inc
Buffalo, NYConstruction & Renovation
Since 20078 agencies
- Contract value
- $4.5M
- Contracts
- 19
- Active
- 0
- A
Jos A Sanders & Sons Inc
Construction & Renovation
Since 20096 agencies
- Contract value
- $13.3M
- Contracts
- 32
- Active
- 2
- A
Highland Masonry and Restoration Incorporated
Construction & Renovation
Since 20155 agencies
- Contract value
- $4.0M
- Contracts
- 7
- Active
- 1
- A
Picone Construction Corporation
Construction & Renovation
Since 20107 agencies
- Contract value
- $22.2M
- Contracts
- 10
- Active
- 2
- More construction & renovation contractors Ranked by contract value
Browse more
- Office of General Services - Design & Construction contractors
- SUNY at Buffalo contractors
- Dormitory Authority of the State of New York contractors
- College at Buffalo contractors
- Construction & Renovation contractors
- Top contractors
- All contractors
Contract figures are public New York State contract records as of Nov 13, 2026: current contract amounts and spending to date as reported. Company details are shown when we can match this contractor to a registered business with confidence.
RFP Detector is an independent service and is not affiliated with any government agency. Scores are informational.