Family Danz Heating & Air Conditioning Inc holds 22 contracts worth $5.6M with 4 New York State agencies, most with Office of General Services - Design & Construction; none active today. The first started in 2009.
- Total contract value
- $5.6M
- Current contract amounts
- Spent to date
- $5.1M
- 93% of contract value
- Active contracts
- 0
- None active today
- Contracts on record
- 22
- Since 2009
- Agencies served
- 4
- Most with Office of General Services - Design & Construction
- Years active
- 17
- First contract 2009
Contact & company
Business information and how to reach the company.
Contracts
22 contracts with New York State agencies, active first. Open a row for the full record.
| Details | Contract | Type | Contract no. | Term | |||||
|---|---|---|---|---|---|---|---|---|---|
Provide parking garage elevator, Bldg. no.3 @ Capital District PC DM2927HConstruction: Building | Office of General Services - Design & Construction | Construction: BuildingConstruction | DM2927H | Nov 27, 2013to Sep 12, 2015 | Nov 27, 2013 | Sep 12, 2015 | $53,855$52,154 spent | $52,154 | |
Replace emergency generators & switchgear power house building 17 mid state CF D44306HConstruction: Building | Office of General Services - Design & Construction | Construction: BuildingConstruction | D44306H | Sep 25, 2013to Oct 13, 2016 | Sep 25, 2013 | Oct 13, 2016 | $150,529$146,958 spent | $146,958 | |
Provide upgrade to heating system DOT region 8 maintenance subheadquarters columbia county D44346HConstruction: Building | Office of General Services - Design & Construction | Construction: BuildingConstruction | D44346H | May 31, 2013to Oct 12, 2014 | May 31, 2013 | Oct 12, 2014 | $280,135$279,949 spent | $279,949 | |
Mechanical work for the parame T000342Contract not subject to state pre-audit | College of Agriculture and Technology at Cobleskill | Contract not subject to state pre-auditNot pre-audited | T000342 | May 24, 2013to Jul 19, 2013 | May 24, 2013 | Jul 19, 2013 | $43,725$43,725 spent | $43,725 | |
ELEVATOR MODERNIZATION/REPAIR at DMNA Headquarters, Latham, NY DQ1510HConstruction: Building | Office of General Services - Design & Construction | Construction: BuildingConstruction | DQ1510H | May 6, 2013to May 31, 2014 | May 6, 2013 | May 31, 2014 | $15,489$13,889 spent | $13,889 | |
Chiller replacement senate house state historic site museum kingston NY D004332Construction: Building | Office of Parks Recreation & Historic Preservation | Construction: BuildingConstruction | D004332 | Apr 25, 2013to Sep 22, 2013 | Apr 25, 2013 | Sep 22, 2013 | $45,675$41,358 spent | $41,358 | |
HVAC chiller and controls replacement schuyler mansion state historic site D004328Construction: Building | Office of Parks Recreation & Historic Preservation | Construction: BuildingConstruction | D004328 | Mar 6, 2013to Aug 30, 2013 | Mar 6, 2013 | Aug 30, 2013 | $51,710$50,210 spent | $50,210 | |
Repair failed HVAC air handling unit building 71 coxsackie correctional facility DEC185HConstruction: Building | Office of General Services - Design & Construction | Construction: BuildingConstruction | DEC185H | Jan 3, 2013to Dec 31, 2013 | Jan 3, 2013 | Dec 31, 2013 | $200,000$24,886 spent | $24,886 | |
Moreau Lk SP (SC)1of4 Mech T004286Contract not subject to state pre-audit | Office of Parks Recreation & Historic Preservation | Contract not subject to state pre-auditNot pre-audited | T004286 | Nov 1, 2012to May 3, 2013 | Nov 1, 2012 | May 3, 2013 | $34,950$34,950 spent | $34,950 | |
Restore failed ac-15 fan scroll capital district PC DEC065HConstruction: Building | Office of General Services - Design & Construction | Construction: BuildingConstruction | DEC065H | Oct 24, 2012to Oct 18, 2013 | Oct 24, 2012 | Oct 18, 2013 | $100,000$75,551 spent | $75,551 | |
Rehab mechanical rooms various bldgs greene CF D44075HConstruction: Building | Office of General Services - Design & Construction | Construction: BuildingConstruction | D44075H | May 1, 2012to May 17, 2014 | May 1, 2012 | May 17, 2014 | $750,983$731,351 spent | $731,351 | |
Replace boiler and DDC controls in troy armory troy, new york DQ1438HConstruction: Building | Office of General Services - Design & Construction | Construction: BuildingConstruction | DQ1438H | Dec 15, 2011to May 18, 2014 | Dec 15, 2011 | May 18, 2014 | $1,120,651$1,120,014 spent | $1,120,014 | |
Provide water treatment plant improvements coxsackie CF D44026HConstruction: Building | Office of General Services - Design & Construction | Construction: BuildingConstruction | D44026H | Oct 13, 2011to Aug 9, 2012 | Oct 13, 2011 | Aug 9, 2012 | $25,985$24,838 spent | $24,838 | |
Construction of complete HVAC system at five river s ed center-guided school BLDG D008224Construction: Building | Department of Environmental Conservation | Construction: BuildingConstruction | D008224 | Sep 30, 2011to Aug 3, 2012 | Sep 30, 2011 | Aug 3, 2012 | $47,000$41,705 spent | $41,705 | |
Repair ice damaged boiler stacks hale creek CF DEB481HConstruction: Building | Office of General Services - Design & Construction | Construction: BuildingConstruction | DEB481H | Mar 15, 2011to Jul 13, 2011 | Mar 15, 2011 | Jul 13, 2011 | $100,000$2,877 spent | $2,877 | |
Repair leaking steam line room B9 albany training academy DEB442HConstruction: Building | Office of General Services - Design & Construction | Construction: BuildingConstruction | DEB442H | Dec 29, 2010to Apr 28, 2011 | Dec 29, 2010 | Apr 28, 2011 | $100,000$35,164 spent | $35,164 | |
Northampton beach campground shower buildings T900013Contract not subject to state pre-audit | Department of Environmental Conservation | Contract not subject to state pre-auditNot pre-audited | T900013 | Nov 15, 2010to Jul 18, 2011 | Nov 15, 2010 | Jul 18, 2011 | $16,300$15,300 spent | $15,300 | |
Provide construction work to restore second floor offices-utica state ob D44212HConstruction: Building | Office of General Services - Design & Construction | Construction: BuildingConstruction | D44212H | Oct 1, 2010to Jun 16, 2011 | Oct 1, 2010 | Jun 16, 2011 | $96,250$94,590 spent | $94,590 | |
Weld shop ventilation system HVAC work washington CF D43879HConstruction: Building | Office of General Services - Design & Construction | Construction: BuildingConstruction | D43879H | Aug 13, 2010to Oct 26, 2012 | Aug 13, 2010 | Oct 26, 2012 | $211,045$203,813 spent | $203,813 | |
Upgrade elevators, BLDG. no 7a state ob campus D43608HConstruction: Building | Office of General Services - Design & Construction | Construction: BuildingConstruction | D43608H | Sep 16, 2009to Jul 30, 2011 | Sep 16, 2009 | Jul 30, 2011 | $59,833$58,092 spent | $58,092 |
Provide parking garage elevator, Bldg. no.3 @ Capital District PCOffice of General Services - Design & ConstructionNov 27, 2013 – Sep 12, 2015$53,855
- Description
- Provide parking garage elevator, Bldg. no.3 @ Capital District PC
- Contract number
- DM2927H
- Type
- Construction: BuildingConstruction
- Term
- Nov 27, 2013 → Sep 12, 20151.8 years
- Approved
- Nov 27, 2013
- Status
- Ended
- Amount
- $53,855
- Spent to date
- $52,154 · 97% of the amount
Replace emergency generators & switchgear power house building 17 mid state CFOffice of General Services - Design & ConstructionSep 25, 2013 – Oct 13, 2016$150,529
- Description
- Replace emergency generators & switchgear power house building 17 mid state CF
- Contract number
- D44306H
- Type
- Construction: BuildingConstruction
- Term
- Sep 25, 2013 → Oct 13, 20163.1 years
- Approved
- Sep 25, 2013
- Status
- Ended
- Amount
- $150,529
- Spent to date
- $146,958 · 98% of the amount
Provide upgrade to heating system DOT region 8 maintenance subheadquarters columbia countyOffice of General Services - Design & ConstructionMay 31, 2013 – Oct 12, 2014$280,135
- Description
- Provide upgrade to heating system DOT region 8 maintenance subheadquarters columbia county
- Contract number
- D44346H
- Type
- Construction: BuildingConstruction
- Term
- May 31, 2013 → Oct 12, 201416 months
- Approved
- May 31, 2013
- Status
- Ended
- Amount
- $280,135
- Spent to date
- $279,949 · 100% of the amount
Mechanical work for the parameCollege of Agriculture and Technology at CobleskillMay 24, 2013 – Jul 19, 2013$43,725
- Description
- Mechanical work for the parame
- Contract number
- T000342
- Type
- Contract not subject to state pre-auditNot pre-audited
- Term
- May 24, 2013 → Jul 19, 20132 months
- Approved
- Aug 13, 2013
- Status
- Ended
- Amount
- $43,725
- Spent to date
- $43,725 · 100% of the amount
ELEVATOR MODERNIZATION/REPAIR at DMNA Headquarters, Latham, NYOffice of General Services - Design & ConstructionMay 6, 2013 – May 31, 2014$15,489
- Description
- ELEVATOR MODERNIZATION/REPAIR at DMNA Headquarters, Latham, NY
- Contract number
- DQ1510H
- Type
- Construction: BuildingConstruction
- Term
- May 6, 2013 → May 31, 201413 months
- Approved
- May 6, 2013
- Status
- Ended
- Amount
- $15,489
- Spent to date
- $13,889 · 90% of the amount
Chiller replacement senate house state historic site museum kingston NYOffice of Parks Recreation & Historic PreservationApr 25, 2013 – Sep 22, 2013$45,675
- Description
- Chiller replacement senate house state historic site museum kingston NY
- Contract number
- D004332
- Type
- Construction: BuildingConstruction
- Term
- Apr 25, 2013 → Sep 22, 20135 months
- Approved
- Apr 25, 2013
- Status
- Ended
- Amount
- $45,675
- Spent to date
- $41,358 · 91% of the amount
HVAC chiller and controls replacement schuyler mansion state historic siteOffice of Parks Recreation & Historic PreservationMar 6, 2013 – Aug 30, 2013$51,710
- Description
- HVAC chiller and controls replacement schuyler mansion state historic site
- Contract number
- D004328
- Type
- Construction: BuildingConstruction
- Term
- Mar 6, 2013 → Aug 30, 20136 months
- Approved
- Mar 6, 2013
- Status
- Ended
- Amount
- $51,710
- Spent to date
- $50,210 · 97% of the amount
Repair failed HVAC air handling unit building 71 coxsackie correctional facilityOffice of General Services - Design & ConstructionJan 3, 2013 – Dec 31, 2013$200,000
- Description
- Repair failed HVAC air handling unit building 71 coxsackie correctional facility
- Contract number
- DEC185H
- Type
- Construction: BuildingConstruction
- Term
- Jan 3, 2013 → Dec 31, 201312 months
- Approved
- Feb 19, 2013
- Status
- Ended
- Amount
- $200,000
- Spent to date
- $24,886 · 12% of the amount
Moreau Lk SP (SC)1of4 MechOffice of Parks Recreation & Historic PreservationNov 1, 2012 – May 3, 2013$34,950
- Description
- Moreau Lk SP (SC)1of4 Mech
- Contract number
- T004286
- Type
- Contract not subject to state pre-auditNot pre-audited
- Term
- Nov 1, 2012 → May 3, 20136 months
- Approved
- Nov 6, 2012
- Status
- Ended
- Amount
- $34,950
- Spent to date
- $34,950 · 100% of the amount
Restore failed ac-15 fan scroll capital district PCOffice of General Services - Design & ConstructionOct 24, 2012 – Oct 18, 2013$100,000
- Description
- Restore failed ac-15 fan scroll capital district PC
- Contract number
- DEC065H
- Type
- Construction: BuildingConstruction
- Term
- Oct 24, 2012 → Oct 18, 201312 months
- Approved
- Nov 16, 2012
- Status
- Ended
- Amount
- $100,000
- Spent to date
- $75,551 · 76% of the amount
Rehab mechanical rooms various bldgs greene CFOffice of General Services - Design & ConstructionMay 1, 2012 – May 17, 2014$750,983
- Description
- Rehab mechanical rooms various bldgs greene CF
- Contract number
- D44075H
- Type
- Construction: BuildingConstruction
- Term
- May 1, 2012 → May 17, 20142.1 years
- Approved
- Oct 24, 2011
- Status
- Ended
- Amount
- $750,983
- Spent to date
- $731,351 · 97% of the amount
Replace boiler and DDC controls in troy armory troy, new yorkOffice of General Services - Design & ConstructionDec 15, 2011 – May 18, 2014$1,120,651
- Description
- Replace boiler and DDC controls in troy armory troy, new york
- Contract number
- DQ1438H
- Type
- Construction: BuildingConstruction
- Term
- Dec 15, 2011 → May 18, 20142.4 years
- Approved
- Dec 15, 2011
- Status
- Ended
- Amount
- $1,120,651
- Spent to date
- $1,120,014 · 100% of the amount
Provide water treatment plant improvements coxsackie CFOffice of General Services - Design & ConstructionOct 13, 2011 – Aug 9, 2012$25,985
- Description
- Provide water treatment plant improvements coxsackie CF
- Contract number
- D44026H
- Type
- Construction: BuildingConstruction
- Term
- Oct 13, 2011 → Aug 9, 201210 months
- Approved
- Oct 13, 2011
- Status
- Ended
- Amount
- $25,985
- Spent to date
- $24,838 · 96% of the amount
Construction of complete HVAC system at five river s ed center-guided school BLDGDepartment of Environmental ConservationSep 30, 2011 – Aug 3, 2012$47,000
- Description
- Construction of complete HVAC system at five river s ed center-guided school BLDG
- Contract number
- D008224
- Type
- Construction: BuildingConstruction
- Term
- Sep 30, 2011 → Aug 3, 201210 months
- Approved
- Mar 14, 2012
- Status
- Ended
- Amount
- $47,000
- Spent to date
- $41,705 · 89% of the amount
Repair ice damaged boiler stacks hale creek CFOffice of General Services - Design & ConstructionMar 15, 2011 – Jul 13, 2011$100,000
- Description
- Repair ice damaged boiler stacks hale creek CF
- Contract number
- DEB481H
- Type
- Construction: BuildingConstruction
- Term
- Mar 15, 2011 → Jul 13, 20114 months
- Approved
- Mar 18, 2011
- Status
- Ended
- Amount
- $100,000
- Spent to date
- $2,877 · 3% of the amount
Repair leaking steam line room B9 albany training academyOffice of General Services - Design & ConstructionDec 29, 2010 – Apr 28, 2011$100,000
- Description
- Repair leaking steam line room B9 albany training academy
- Contract number
- DEB442H
- Type
- Construction: BuildingConstruction
- Term
- Dec 29, 2010 → Apr 28, 20114 months
- Approved
- Feb 14, 2011
- Status
- Ended
- Amount
- $100,000
- Spent to date
- $35,164 · 35% of the amount
Northampton beach campground shower buildingsDepartment of Environmental ConservationNov 15, 2010 – Jul 18, 2011$16,300
- Description
- Northampton beach campground shower buildings
- Contract number
- T900013
- Type
- Contract not subject to state pre-auditNot pre-audited
- Term
- Nov 15, 2010 → Jul 18, 20118 months
- Approved
- Nov 5, 2010
- Status
- Ended
- Amount
- $16,300
- Spent to date
- $15,300 · 94% of the amount
Provide construction work to restore second floor offices-utica state obOffice of General Services - Design & ConstructionOct 1, 2010 – Jun 16, 2011$96,250
- Description
- Provide construction work to restore second floor offices-utica state ob
- Contract number
- D44212H
- Type
- Construction: BuildingConstruction
- Term
- Oct 1, 2010 → Jun 16, 20118 months
- Approved
- Oct 1, 2010
- Status
- Ended
- Amount
- $96,250
- Spent to date
- $94,590 · 98% of the amount
Weld shop ventilation system HVAC work washington CFOffice of General Services - Design & ConstructionAug 13, 2010 – Oct 26, 2012$211,045
- Description
- Weld shop ventilation system HVAC work washington CF
- Contract number
- D43879H
- Type
- Construction: BuildingConstruction
- Term
- Aug 13, 2010 → Oct 26, 20122.2 years
- Approved
- Dec 13, 2011
- Status
- Ended
- Amount
- $211,045
- Spent to date
- $203,813 · 97% of the amount
Upgrade elevators, BLDG. no 7a state ob campusOffice of General Services - Design & ConstructionSep 16, 2009 – Jul 30, 2011$59,833
- Description
- Upgrade elevators, BLDG. no 7a state ob campus
- Contract number
- D43608H
- Type
- Construction: BuildingConstruction
- Term
- Sep 16, 2009 → Jul 30, 20111.8 years
- Approved
- Feb 23, 2011
- Status
- Ended
- Amount
- $59,833
- Spent to date
- $58,092 · 97% of the amount
Contract-type mix
Share of contract value by type
- Construction: Building19 contracts$5.5M
- Contract not subject to state pre-audit3 contracts$95.0K
Contracts over time
Contracts started per year
View as table
| Year | Contracts |
|---|---|
| 2009: 3 contracts, $2.1M | 3 |
| 2010: 4 contracts, $423.6K | 4 |
| 2011: 4 contracts, $1.3M | 4 |
| 2012: 3 contracts, $885.9K | 3 |
| 2013: 8 contracts, $841.1K | 8 |
| 2014: 0 contracts, $0.0 | 0 |
| 2015: 0 contracts, $0.0 | 0 |
| 2016: 0 contracts, $0.0 | 0 |
| 2017: 0 contracts, $0.0 | 0 |
| 2018: 0 contracts, $0.0 | 0 |
| 2019: 0 contracts, $0.0 | 0 |
| 2020: 0 contracts, $0.0 | 0 |
| 2021: 0 contracts, $0.0 | 0 |
| 2022: 0 contracts, $0.0 | 0 |
| 2023: 0 contracts, $0.0 | 0 |
| 2024: 0 contracts, $0.0 | 0 |
| 2025: 0 contracts, $0.0 | 0 |
| 2026: 0 contracts, $0.0 | 0 |
How the Contractor Score adds up
Established (B, 69/100): $5.6M in contracts, works with 4 agencies; but no contract since 2013.
- Contract volume+8.4measured
$5.6M in current contract value across 22 contracts, more than 81% of scored contractors.
- Recent activity−4.4measured
No active contracts today; the most recent was approved in November 2013.
- Agency breadth+8.3measured
Contracts with 4 different state agencies and facilities.
- Experience+1.8measured
First contract started in April 2009 (17 years of contract history).
- Contract-type mix+5.1measured
2 contract types; the largest group is construction (98% of value). Goods and services contracts are 98% of the total.
- Spending vs. value0.0measured
On 22 completed contracts with spending recorded, spending is 93% of the contract value. Spending below the full value is common (work can finish under budget) and isn't treated as a problem.
- Federal award history0.0unknown
No federal award history found. Scored as neutral.
- Federal registration0.0unknown
No federal contractor registration found. Scored as neutral.
50 + contributions = 69 (B, Established)Starts at 50. Bars: cool adds, warm subtracts.
Agencies served
Contract value with each agency or facility
Similar contractors
- B
Tri-Valley Plumbing & Heating Inc
Construction & Renovation
Since 20094 agencies
- Contract value
- $3.8M
- Contracts
- 30
- Active
- 0
- A
Harold R Clune Inc
Ballston Spa, NYConstruction & Renovation
Since 20095 agencies
- Contract value
- $2.7M
- Contracts
- 22
- Active
- 2
- B
General Roofing Contractors LLC
Construction & Renovation
Since 20158 agencies
- Contract value
- $17.2M
- Contracts
- 21
- Active
- 0
- A
Stilsing Electric Inc
Rensselaer, NYConstruction & Renovation
Since 20087 agencies
- Contract value
- $68.4M
- Contracts
- 133
- Active
- 23
- B
J McBain Inc
Troy, NYConstruction & Renovation
Since 20113 agencies
- Contract value
- $6.0M
- Contracts
- 24
- Active
- 0
- A
Palace Electrical Contractors Inc
Farmingdale, NYConstruction & Renovation
Since 20125 agencies
- Contract value
- $5.1M
- Contracts
- 15
- Active
- 0
- More construction & renovation contractors Ranked by contract value
Browse more
- Office of General Services - Design & Construction contractors
- Office of Parks Recreation & Historic Preservation contractors
- Department of Environmental Conservation contractors
- College of Agriculture and Technology at Cobleskill contractors
- Construction & Renovation contractors
- Top contractors
- All contractors
Contract figures are public New York State contract records as of Nov 13, 2026: current contract amounts and spending to date as reported. Company details are shown when we can match this contractor to a registered business with confidence.
RFP Detector is an independent service and is not affiliated with any government agency. Scores are informational.