Knowing how to read an RFP is the skill every winning proposal is built on. Before anyone writes a word, someone has to take the solicitation apart, find every instruction, requirement and scoring rule, and put them in a list the team can work from. Proposal professionals call this shredding an RFP, and the list it produces is the compliance matrix. This chapter shows you how to do both, with a first-read checklist, sample matrix rows and the red flags that should make you stop and think.
The method works for a 400-page federal solicitation and a 12-page school district request alike. Still deciding whether to bid? Use the bid/no-bid decision framework.
Anatomy of an RFP: the six parts that matter
Every solicitation is built from the same blocks. Federal solicitations under FAR Part 15 use the uniform contract format, with lettered sections A through M. State, city and county RFPs number things their own way, but the same pieces are always there.
| Part | What it tells you | Federal (uniform contract format) | Typical state or local name |
|---|---|---|---|
| Scope of work | What the buyer wants done, and to what standard | Section C: statement of work (SOW), performance work statement (PWS) or statement of objectives (SOO) | Scope of services, specifications |
| Instructions | How to organize, format and deliver your proposal | Section L: instructions, conditions and notices to offerors | Submission requirements, instructions to proposers |
| Evaluation criteria | How proposals are scored and the winner chosen | Section M: evaluation factors for award | Evaluation criteria, basis of award |
| Terms and conditions | The contract you sign if you win | Sections B and D to J: prices, delivery, clauses, attachments | Sample contract, general terms |
| Forms and certifications | What you must sign, certify and attach | Section K: representations and certifications, plus the SF 33 or SF 1449 cover form | Required forms, disclosure forms, vendor questionnaires |
| Amendments | Changes after release | Amendments, commonly on Standard Form 30 | Addenda, Q&A bulletins |
Section L can require a set format or separate volumes, and Section M must name the significant evaluation factors and their relative importance. The 2025 to 2026 FAR overhaul renumbers Part 15, but the C, L and M structure carries over.
- Solicitation
The buyer's formal request for offers: an RFP, IFB, RFQ or RFI (see types of solicitations).
- SOW, PWS, SOO
A statement of work says how to do the job, a performance work statement sets results and standards, and a statement of objectives states goals and leaves the approach to you.
- Responsive
Your offer meets the solicitation's requirements and instructions in all material respects.
- Responsible
You can actually perform. New York State law frames it as financial ability, legal capacity, integrity and past performance.
Low bid or best value? Read the basis of award first
Before you shred anything, find the sentence that says how the winner will be picked. It tells you whether evaluators will score your writing at all.
| Question | Low-bid IFB (sealed bidding) | Best-value RFP (negotiated) |
|---|---|---|
| Who wins? | The lowest-priced responsive bid from a responsible bidder | The proposal offering the best overall value under the stated method |
| What is evaluated? | Federal sealed bidding considers only price and price-related factors | Technical approach, management, past performance and price, as weighted |
| What sinks an offer? | A missing form, signature, bond or acknowledgment, or a condition that changes the terms | Ignored instructions, unaddressed requirements, weak proof or an unrealistic price |
| Local example | New York municipalities generally must bid public works over $35,000 and purchases over $20,000 and award to the lowest responsible bidder (as of 2026) | New York State awards most service contracts on best value: optimizing quality, cost and efficiency |
Best value has variants. A federal tradeoff award can go to a higher-priced proposal if its extra benefits are worth the cost. Lowest price technically acceptable (LPTA) checks the technical proposal pass/fail, then picks the lowest price. Put the exact award language at the top of your matrix.
How to read an RFP the first time: a two-hour checklist
Your first read is not for writing. It decides whether you can bid and captures the facts the team will need daily. Read the whole package once, quickly, then fill in this checklist.
How to shred an RFP, step by step
Shredding means going through the solicitation sentence by sentence and pulling every requirement into its own row, in the issuer's words. It is tedious, and it is your best protection against losing on a technicality. Give it to one owner: a committee shred produces gaps and duplicates.
Step 1: Collect and code the package
Give each document a short code (RFP, ATT-A, AMD-1) so every matrix row can cite its source.
Step 2: Search for requirement words
Find and highlight shall, must, will, should, may, required, submit, describe and demonstrate. Embedded questions ('How will the offeror ensure continuity?') are requirements too.
Tip: Read each surrounding paragraph. Requirements also hide in tables and footnotes that a keyword search misses.Step 3: Split compound sentences
'The contractor shall provide a project manager and a quality control plan within 10 days of award' is three requirements. Give each its own row.
Step 4: Record the exact source
Note document, section, page and paragraph, and paste the requirement word for word. Paraphrasing now is how requirements quietly get lost.
Step 5: Tag the type
Instruction, evaluation, scope, form or contract term; then mandatory or desirable.
Step 6: Map to your outline and name an owner
Decide where each requirement is answered and who writes it. Rows with no home signal a missing section; see how to mirror the solicitation.
Step 7: Reconcile and keep it live
Check that every evaluation factor maps to a row and every row to a proposal section. Update the matrix with each amendment, noting the version.
Building the RFP compliance matrix (with sample rows)
The compliance matrix is the output of the shred: a spreadsheet with one row per requirement. Use these columns: ID (a code like L-014 for meetings), source, requirement text (verbatim), type, mandatory or desirable, proposal location, owner (one named person) and status and notes (including the amendment number). Add columns for themes or hot buttons only if they earn their place.
| ID | Source | Requirement (verbatim) | Type | M/D | Proposal location | Owner |
|---|---|---|---|---|---|---|
| L-007 | RFP §4.2, p. 9 | Technical proposals shall not exceed 25 pages, 12-point font, 1-inch margins. | Instruction | M | All of Vol. I | Proposal manager |
| L-012 | RFP §4.3(c), p. 10 | Proposers must submit a Certificate of Insurance meeting Exhibit C limits with the proposal. | Form | M | Vol. III, Tab 4 | Operations lead |
| M-02 | RFP §5.1, p. 12 | Technical approach (40 points): clarity and feasibility of the preventive maintenance program. | Evaluation | D | Vol. I, §2 | Technical lead |
| C-031 | EXH-A §3.4 | The contractor shall respond on site to emergency calls within 2 hours, 24/7/365. | Scope | M | Vol. I, §2.2, Fig. 2-2 | Service manager |
| C-032 | EXH-A §3.4 | Response times shall be reported monthly. | Scope | M | Vol. I, §4.1 | Service manager |
| K-004 | AMD-2, item 3 | Acknowledge Addenda 1 and 2 on Form 7, signed by an authorized officer. | Form | M | Vol. III, Tab 1 | Contracts administrator |
Notice what the sample does. Rows C-031 and C-032 come from one paragraph but are split, so the reporting duty cannot hide behind the response-time promise. Row K-004 exists only because of an amendment, which is why the matrix stays live until you submit.
If you track the RFP in RFP Detector, add critical items (insurance certificate, notarized forms, amendment acknowledgments) to the tracked RFP's Checklist tab so the team sees progress. A copy-ready matrix is in the compliance matrix template.
Mandatory vs desirable requirements
Mandatory requirements are pass/fail gates: miss one and your proposal can be rejected before anyone scores it. Desirable requirements (rated or scored) earn points; missing one costs score, not eligibility. Many state and local RFPs screen mandatory items first and score only the proposals that pass.
| Signal in the text | Usually means | How to treat it |
|---|---|---|
| shall, must, is required | Mandatory | Comply exactly and show where |
| minimum qualifications, pass/fail | Mandatory gate | Prove it with licenses, references, certificates |
| should, preferred, desirable, may | Desirable or scored | Address it if you can; extra points live here |
| points, weights, adjectival ratings | Scored evaluation | Spend pages in proportion to the weight |
The team treats it as a must-have and passes on a contract it could have won.
The team flags it as desirable, finds it is a subfactor worth 5 of 100 points, and adds a subcontractor with that experience to pick up the points.
Questions to the issuer and key deadlines
Almost every RFP sets a window for written questions. Use it: good questions remove ambiguity and sometimes change the solicitation in your favor. Answers usually go to every bidder, so ask without revealing your strategy.
Release
RFP issued
Start the first read and the shred the same day.
Week 1
Pre-proposal conference or site visit
Attend, always if mandatory. Spoken answers bind no one until they appear in a written amendment.
Weeks 1 to 2
Question deadline
Send consolidated, numbered questions in writing to the named contact. Late questions often go unanswered.
Weeks 2 to 3
Answers and amendments
Update your matrix, outline and pricing.
Final days
Proposal due
Submit early. Federal rules treat a proposal arriving after the exact due time as late, with narrow exceptions; many state and local issuers allow none.
Contact rules are strict. New York State's procurement lobbying law sets a restricted period from the start of the solicitation until award, when you may contact only the designated contacts named in the RFP; a knowing and willful violation can lead to a non-responsibility finding that generally bars award. Federally, the contracting officer is the focal point once the RFP is out, and information given to one potential offeror must be made available to all.
Strong question
- Do: Cites the conflict: 'RFP §C.3.4 requires a 2-hour response; Exhibit B, p. 3 says 4 hours. Which governs?'
- Do: Asks for a decision: 'Do résumés count toward the 25-page limit?'
- Do: Suggests a fix: 'Would the County accept insurance certificates at award?'
Weak question
- Don't: Vague: 'Can you tell us more about the scope?'
- Don't: Reveals your solution or pricing to every competitor
- Don't: Is phoned in to a program manager instead of the named contact
Template
Questions to the issuer (submission format)
A full letter version is in the questions to the issuer letter.
When to use it
Send once, before the question deadline, to the named contact by the method the RFP specifies. Use the issuer's own form instead if it provides one.
QUESTIONS REGARDING [SOLICITATION_NUMBER]: [SOLICITATION_TITLE] Submitted by: [COMPANY_LEGAL_NAME] Contact: [CONTACT_NAME], [TITLE], [EMAIL], [PHONE] Date submitted: [DATE] Submitted to: [NAMED_CONTACT], by [METHOD_REQUIRED_BY_RFP] Question 1 Reference: [DOCUMENT], Section [SECTION], Page [PAGE] Text cited: '[EXACT_REQUIREMENT_TEXT]' Question: [YOUR_QUESTION] Suggested clarification (optional): [PROPOSED_CHANGE] (Repeat the block above for each question, numbered in order.) We understand that answers may be shared with all prospective proposers and that only a written amendment changes the solicitation.
Fields to fill in
- [NAMED_CONTACT]
- The contracting officer or designated contact named in the RFP, nobody else
- [EXACT_REQUIREMENT_TEXT]
- Quote the sentence word for word so the issuer knows exactly which requirement you mean
- [PROPOSED_CHANGE]
- A specific, reasonable alternative; leave blank if it would reveal your approach
Tracking amendments and addenda
An amendment (or addendum) changes the solicitation after release: a new due date, a revised price form, an answer that adds a requirement. Under the FAR, the contracting officer must amend the solicitation when requirements or terms change, and offerors must acknowledge each amendment by the time it sets. State and city RFPs work the same way, often with an addenda acknowledgment form.
Step 1: Check every day
Check the issuing portal daily in the final two weeks. In RFP Detector, the 'Tracked RFP amended' notification (in-app and email, on by default) tells you when a due date moves, documents are added or details change on an RFP your organization tracks; the change also shows in the tracked RFP's Activity tab.
Tip: Still confirm against the official solicitation before you submit. Every amendment is your responsibility.Step 2: Log and re-shred
Record the number, date and what changed; add, revise or retire matrix rows; move superseded files to an 'old' folder.
Step 3: Tell the team the same day
A writer working from last week's scope is a classic cause of noncompliance.
Step 4: Acknowledge exactly as instructed
On the cover form, a separate form or in the portal. Federal amendments commonly arrive on Standard Form 30, which has its own acknowledgment block.
Red flags to catch on the first read
Flag these and take them to your bid/no-bid discussion; some are fixable with a good question.
| Red flag | Why it matters | What to do |
|---|---|---|
| Requirements only one firm could meet (a brand name, an oddly specific credential) | The RFP may be written around an incumbent | Ask whether an equivalent is acceptable; weigh your odds honestly |
| Evaluation criteria missing or at odds with the scope | Hard to write to; more protest and cancellation risk | Ask for the weights in writing |
| Unlimited liability or pay-when-paid terms | Risk you cannot insure or finance | Ask whether exceptions are allowed and how they are evaluated |
| Insurance or bonding far above the contract value | Excludes small firms or signals hidden risk | Ask whether limits can be reduced or provided at award |
| A scope far larger than the budget | You lose on price or lose money performing | Price the realistic scope or no-bid |
Frequently asked questions
What does it mean to shred an RFP?
Shredding an RFP means breaking the solicitation into individual requirements, one per row, in the issuer's exact words, with the source of each. The result is a compliance matrix listing every instruction, evaluation criterion, scope requirement, form and contract term, with an owner and the place your proposal answers it.
What is a compliance matrix in a proposal?
A compliance matrix is a table of every requirement in a solicitation with its source, type, whether it is mandatory, the proposal section that answers it and an owner. It drives the outline, the writing assignments and the final check. Some RFPs require a submitted version, called a cross-reference matrix.
What is the difference between Section L and Section M?
In federal solicitations, Section L holds the instructions (how to organize, format and submit) and Section M holds the evaluation factors (what will be assessed and how much each matters). Follow L to stay compliant and write to M to score well. State and local RFPs have the same parts under names like 'submission requirements' and 'evaluation criteria'.
How long does it take to shred an RFP?
A short state or local RFP can take a few hours; a large federal solicitation with many attachments can take an experienced person a day or more. Start on release day: the shred drives your bid decision, questions and outline, and the question deadline often comes early.
What happens if I miss an RFP amendment?
Your proposal can be found nonresponsive and rejected, or evaluated against requirements you did not meet. Read the acknowledgment instructions, keep checking the portal up to the due date and acknowledge every amendment exactly as directed.
Can I contact the agency while an RFP is open?
Only through the channel the solicitation names, usually the contracting officer or a designated contact, and usually in writing during the question period. New York State's procurement lobbying law limits contact during the restricted period to designated contacts. Contacting evaluators or program staff directly can get you disqualified.
What is the difference between mandatory and desirable requirements?
Mandatory requirements are pass/fail and usually say 'shall', 'must' or 'is required'; missing one can get your proposal rejected unscored. Desirable requirements are scored or optional: meeting them earns points. When the wording is unclear, treat the requirement as mandatory and ask.
Complete handbook
Download the complete handbook (PDF)
All 8 chapters, templates and checklists, ready to print or share.
Put it into practice
Search open RFPs from federal, state, local, education, private and non-profit issuers, each with the RFP Detector Score.